Which of the following statements is true about a critical path?
A) A critical path consists of activities for which early start time equals late start time.
B) The activities along the critical path take the longest time.
C) A critical path consists of activities for which early finish time equals late finish time.
D) There is no slack in the activities along the critical path.
E) All of the above