Multiple Choice
Which of the following statements is incorrect about the PERT method of project scheduling?
A) PERT requires three time estimates for scheduling a given activity.
B) PERT assumes that the actual activity times are distributed according to the beta probability distribution.
C) PERT assumes that the statistical variation in total project completion times can be computed by multiplying variances along the critical path.
D) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q7: A forward pass of the above network
Q11: Which of the following statements about CPM
Q12: "Slack" refers to the difference between:<br>A)Late and
Q13: Controlling a project does NOT entail:<br>A)Monitoring costs,time,and
Q15: Estimating the time required for each task
Q17: Which of the following statements is true
Q18: A work breakdown structure is used in
Q19: A network-based project scheduling method that requires
Q23: The early start and late start times
Q25: A forward pass is required while computing