Multiple Choice
Multiple critical paths can exist under CPM because:
A) There is more than one way to complete the project
B) Different network paths exist,each with the same total time
C) Great flexibility of activity sequences is available
D) None of the above
Correct Answer:

Verified
Correct Answer:
Verified