    A Project Consists of the Following Four Activities with Activity
Solved

A Project Consists of the Following Four Activities with Activity

Question 33

Question 33

Multiple Choice

A project consists of the following four activities with activity times in days:
A project consists of the following four activities with activity times in days:    Table YY -Using Table YY,the earliest start (ES) time for activity B is A) 5 days. B) 6 days. C) 11 days. D) 14 days. Table YY
-Using Table YY,the earliest start (ES) time for activity B is


A) 5 days.
B) 6 days.
C) 11 days.
D) 14 days.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q28: A project consists of the following activities:<br>

Q29: A project consists of the following four

Q30: Project scope,one of the basic elements of

Q31: Global projects are rarely concerned with cultural

Q32: In general,the latest finish time for an

Q34: Microsoft Project is a software package that

Q35: A project consists of the following activities:<br>

Q36: Activities that are not on a project's

Q37: The upper level of a work breakdown

Q38: A bar graph displaying when activities are

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines