Multiple Choice
A project consists of the following activities:
Table XX
-Using Table XX,the earliest finish (EF) time for activity D is
A) 7 weeks.
B) 13 weeks.
C) 20 weeks.
D) 30 weeks.
Correct Answer:

Verified
Correct Answer:
Verified