A project consists of the following four activities with activity times in days:
Table YY
-Using Table YY,the critical path for this project is
A) A-B-C.
B) A-C-D.
C) A-B-D.
D) A-B-C-D.
Correct Answer:

Verified
Correct Answer:
Verified