Multiple Choice
The estimated variance for an activity with a most likely time (m) equal to 11 days,the optimistic time (a) equal to 6 days,and the pessimistic time (b) equal to 18 days is
A) 2 days.
B) 4 days.
C) 6 days.
D) 11 days.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q61: The following table of probabilistic time estimates
Q62: In general,the earliest finish time for an
Q63: Which of the following statements is generally
Q64: One disadvantage of Gantt charts,especially for large
Q65: Issues of cultural diversity in project management
Q67: Control,one of the basic elements of a
Q68: The three primary elements of project management
Q69: A project consists of the following activities:<br>
Q70: Indirect costs always increase as a project's
Q71: What is a scope statement?