Multiple Choice
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
Table ZZ
-Using Table ZZ,the earliest start (ES) time for activity D is
A) 8.17 weeks.
B) 12.67 weeks.
C) 18.33 weeks.
D) 21.67 weeks.
Correct Answer:

Verified
Correct Answer:
Verified