Which of these statements regarding time-cost tradeoffs in CPM networks is true?
A) Crashing is not possible unless there are multiple critical paths.
B) Crashing a project often reduces the length of long-duration,but noncritical,activities.
C) Activities not on the critical path can never be on the critical path,even after crashing.
D) Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
E) The crash time always exceeds the normal time.
Correct Answer:

Verified
Correct Answer:
Verified
Q22: The _ distribution is used by PERT
Q29: PERT calculations typically include the duration variance
Q34: The main difference between PERT and CPM
Q57: A project being analyzed by PERT has
Q58: Which of the following statements regarding PERT
Q61: Project management at the Tour de France
Q87: What are the earliest activity start time
Q92: Identify the responsibilities of project managers.
Q109: A project organization:<br>A) is effective for companies
Q119: The critical path can be determined by