Multiple Choice
Project management at the Tour de France races can be complex because:
A) a team is like a "large travelling circus."
B) there is a wide variety of support staff.
C) there are races being held simultaneously.
D) each team has over two dozen riders.
E) all of the above
Correct Answer:

Verified
Correct Answer:
Verified