Multiple Choice
Which of the following statements concerning CPM activities is false?
A) The early finish of an activity is the early start of that activity plus its duration.
B) The late finish is the earliest of the late start times of all successor activities.
C) The late start of an activity is its late finish less its duration.
D) The late finish of an activity is the earliest late start of all preceding activities.
E) The early start of an activity is the latest early finish of all preceding activities.
Correct Answer:

Verified
Correct Answer:
Verified
Q109: A project organization:<br>A) is effective for companies
Q110: A network consists of the following list.
Q111: In PERT, project variance is computed by
Q112: Which of the following statements regarding PERT
Q113: _ is the amount of time an
Q115: Which of the following is NOT one
Q116: Given the critical path below, calculate the
Q117: Shortening the project's duration by deleting unnecessary
Q118: A project organization that becomes permanent is
Q119: The critical path can be determined by