Essay
The network below represents a project being analyzed by the critical path method.Activity durations are A=5,B=2,C=12,D=3,E=5,F=1,G=7,H=2,I=10,and J=6. a.What task must be on the critical path,regardless of activity durations?
b.What is the duration of path A-B-E-H-J?
c.What is the critical path of this network?
d.What is the length of the critical path?
e.What is slack time at activity H?
f.What is the Late Finish of activity H?
g.If activity C were delayed by two time units,what would happen to the project duration?
Correct Answer:

Verified
(a)J; (b)20; (c)A-B-...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q9: A contractor's project being analyzed by PERT
Q22: The _ distribution is used by PERT
Q29: PERT calculations typically include the duration variance
Q35: Which of the following statements regarding critical
Q57: The expected activity time in PERT analysis
Q59: Which of these statements regarding time-cost tradeoffs
Q106: The network below represents a project being
Q107: Consider the network described in the table
Q110: Which of the following statements regarding Gantt
Q118: A project organization that becomes permanent is