Multiple Choice
Which of the following statements regarding PERT times is true?
A) The expected time is an estimate of the time an activity will require if everything goes as planned.
B) The optimistic time estimate is an estimate of the maximum time an activity will require.
C) The expected time estimate is calculated as t = (a + 4m + b) /6.
D) The pessimistic time estimate is an estimate of the minimum time an activity will require.
E) The most likely time estimate is an estimate of the maximum time an activity will require.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: A project manager determined that the project
Q2: Which of the following statements regarding critical
Q3: In project management, crashing an activity must
Q4: Pirmin's Bike Shop is behind on a
Q6: Which of the following statements regarding PERT
Q7: A project being analyzed by PERT has
Q8: Given the project within the table below,
Q9: Ethical issues that may arise in projects
Q10: Describe agile projects.
Q11: Project management at the Tour de France