A Project Being Analyzed by PERT Has 38 Activities,16 of Which

Question 57

Multiple Choice

A project being analyzed by PERT has 38 activities,16 of which are on the critical path.If the estimated time along the critical path is 90 days with a project variance of 25,what is the probability that the project will be completed in 88 days or less?


A) 0.0228
B) 0.3446
C) 0.6554
D) 0.9772
E) 18