Multiple Choice
There are three consecutive steps in a customer service process.The first two steps are each capable of serving 25 customers per hour while the third step can process only 20 customers per hour.Which of the following statements regarding this system is true?
A) The entire system is capable of processing 25 customers per hour.
B) There are floating bottlenecks in the system.
C) If the first two steps are run at full capacity,then the third step has a waiting line.
D) The first and second steps are bottlenecks for the system.
Correct Answer:

Verified
Correct Answer:
Verified
Q12: Table 7.7<br>A company makes four products that
Q13: Table 7.4 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 7.4
Q14: A business school with plenty of classroom
Q16: Table 7.7<br>A company makes four products that
Q19: Table 7.5<br>A company makes four products that
Q21: Table 7.8<br>King Supply makes four different types
Q22: With TOC,_ are scheduled to maximize their
Q56: Variability of a firm's workload may create
Q119: What are two ways a process manager
Q131: What is the definition of "theoretical maximum