Multiple Choice
Table 7.5
A company makes four products that have the following characteristics: Product A sells for $50 but needs $10 of materials and $15 of labor to produce;Product B sells for $75 but needs $30 of materials and $15 of labor to produce;Product C sells for $100 but needs $50 of materials and $30 of labor to produce;Product D sells for $150 but needs $75 of materials and $40 of labor to produce.The processing requirements for each product on each of the four machines are shown in the table. Work centers W,X,Y,and Z are available for 40 hours per week and have no setup time when switching between products.Market demand for each product is 80 units per week.In the questions that follow,the traditional method refers to maximizing the contribution margin per unit for each product,and the bottleneck method refers to maximizing the contribution margin per minute at the bottleneck for each product.
-Use the information in Table 7.5.Which work center is of greatest concern to the operations manager?
A) Work Center W
B) Work Center X
C) Work Center Y
D) Work Center Z
Correct Answer:

Verified
Correct Answer:
Verified
Q14: A business school with plenty of classroom
Q16: Table 7.7<br>A company makes four products that
Q17: There are three consecutive steps in a
Q21: Table 7.8<br>King Supply makes four different types
Q22: With TOC,_ are scheduled to maximize their
Q23: Balance the line in order to achieve
Q52: A mixed-model line produces several items belonging
Q56: Variability of a firm's workload may create
Q119: What are two ways a process manager
Q131: What is the definition of "theoretical maximum