Multiple Choice
Table 7.7
A company makes four products that have the following characteristics: Product A sells for $75 but needs $20 of materials and $20 of labor to produce;Product B sells for $90 but needs $45 of materials and $20 of labor to produce;Product C sells for $110 but needs $50 of materials and $30 of labor to produce;Product D sells for $135 but needs $75 of materials and $40 of labor to produce.The processing requirements for each product on each of the four machines are shown in the table. Work centers W,X,Y,and Z are available for 40 hours per week and have no setup time when switching between products.Market demand is 50 As,60 Bs,70 Cs,and 80 Ds per week.In the questions that follow,the traditional method refers to maximizing the contribution margin per unit for each product,and the bottleneck method refers to maximizing the contribution margin per minute at the bottleneck for each product.
-Use the information in Table 7.7.Which work center is the bottleneck operation?
A) Work Center W
B) Work Center X
C) Work Center Y
D) Work Center Z
Correct Answer:

Verified
Correct Answer:
Verified
Q4: How can Theory of Constraints principles be
Q12: Table 7.7<br>A company makes four products that
Q13: Table 7.4 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 7.4
Q14: A business school with plenty of classroom
Q17: There are three consecutive steps in a
Q19: Table 7.5<br>A company makes four products that
Q21: Table 7.8<br>King Supply makes four different types
Q56: Variability of a firm's workload may create
Q119: What are two ways a process manager
Q131: What is the definition of "theoretical maximum