Multiple Choice
Fun Vehicles, Inc. makes beach buggies on an assembly line. The total productive time to make one buggy is 300 seconds. The current line has a 90-second cycle time and consists of four workstations. The balance delay of this line must be:
A) 0%.
B) greater than 0% but less than 6%.
C) greater than 6% but less than 12%.
D) greater than 12% but less than 18%.
Correct Answer:

Verified
Correct Answer: