Question 126

Question 126

Multiple Choice

Fig.2.1 Fig.2.1   -For the network shown in Fig.2.1,which of the following is the critical path? A) ABCDEF B) ABEF C) ACDF D) ACEF
-For the network shown in Fig.2.1,which of the following is the critical path?


A) ABCDEF
B) ABEF
C) ACDF
D) ACEF

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q5: The _ is determined by starting with

Q49: The network diagram is a planning method

Q71: _ is an attempt to reduce the

Q81: Following are four sets of most optimistic,

Q92: The probability that a project will be

Q101: Information accuracy relative to the completeness of

Q117: Projects, and the application of project management,

Q121: Project close out consists of a)completing the

Q126: The earliest start time for an activity

Q129: Table 2.4<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 2.4

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines