Multiple Choice
Table 2.4
-Using Table 2.4,what is the minimum number of activities that would have to be delayed to cause an increase in the project's earliest completion date?
A) one activity
B) two activities
C) three activities
D) four or more activities
Correct Answer:

Verified
Correct Answer:
Verified