Multiple Choice
Table 2.3
-Using Table 2.3,what is the earliest expected time of completion of the whole project?
A) fewer than or equal to 21 days
B) greater than 21 but fewer than or equal to 22 days
C) greater than 22 but fewer than or equal to 23 days
D) greater than 23 days
Correct Answer:

Verified
Correct Answer:
Verified