There are three consecutive steps in a customer service process.The first two steps are each capable of serving 25 customers per hour while the third step can process only 20 customers per hour.Which of the following statements regarding this system is TRUE?
A) The entire system is capable of processing 25 customers per hour.
B) There are floating bottlenecks in the system.
C) If the first two steps are run at full capacity,then the third step has a waiting line.
D) The first and second steps are bottlenecks for the system.
Correct Answer:

Verified
Correct Answer:
Verified
Q8: Table 5.2<br>A company makes four products that
Q25: Table 5.1<br>A company makes four products that
Q29: Which statement about process batches is BEST?<br>A)One
Q30: Balance the assembly line using the following
Q33: The second step in Theory of Constraints
Q37: Table 5.1<br>A company makes four products that
Q75: What is a Drum-Buffer-Rope system for planning
Q85: A(n) _ is an operation that has
Q112: The balance delay is the amount by
Q117: According to the Theory of Constraints, all