Which of the following statements regarding time-cost tradeoffs in CPM networks is false?
A) "Project Crashing" shortens project duration by assigning more resources to critical tasks.
B) Crashing sometimes has the reverse result of lengthening the project duration.
C) Crashing must consider the impact of crashing an activity on all paths in the network.
D) Activities not on the critical path can become critical after crashing takes place.
E) All of the above are false.
Correct Answer:

Verified
Correct Answer:
Verified
Q12: Gantt charts give a timeline for each
Q14: Every network has at least one critical
Q35: Which of the following statements regarding critical
Q35: What is the basic difference between PERT
Q74: The Beta distribution is used in project
Q91: An activity on a PERT network has
Q92: Identify the responsibilities of project managers.
Q112: Three critical path activities are candidates for
Q119: The critical path for the network activities
Q120: How is the expected completion time of