When tasks must be completed one after another, they are called concurrent tasks.

Free
(True/False)
4.8/5
(35)
Correct Answer:
Verified

False

Most managers recognize that problems do occur on most projects; it is better to alert management sooner rather than later.

Free
(True/False)
4.8/5
(27)
Correct Answer:
Verified

True

A _____ cannot be started until one or more other tasks are completed.

Free
(Multiple Choice)
4.8/5
(32)
Correct Answer:
Verified

A

A(n) ____________________ is a recognizable reference point that can be used to monitor progress and manage a project.

(Short Answer)
4.8/5
(42)

Gantt charts are an ideal tool for controlling a complex project because they provide plenty of detailed information.

(True/False)
4.9/5
(47)

All of the following are possible causes of cost overruns related to human resource factors EXCEPT ____.

(Multiple Choice)
4.9/5
(36)

Although a Gantt chart provides more detailed information about a project, a PERT/CPM chart offers a rapid overview that graphically displays the timing, duration, and progress of each task.

(True/False)
4.8/5
(40)

The ____________________ is the time that a task is scheduled to be completed.

(Short Answer)
4.8/5
(36)

A project is based on a pattern of ____________________.

(Short Answer)
5.0/5
(31)

A(n) ____________________ is a review of a project team member's work by other members of the team.

(Short Answer)
4.8/5
(38)

In any project, large or small, tasks depend on each other and must be performed in a sequence.

(True/False)
4.7/5
(36)

Project managers always must be aware of the ____ path, so they can monitor the vital tasks and keep the project on track.

(Multiple Choice)
4.8/5
(27)

MATCHING Identify the letter of the choice that best matches the phrase or definition. -The kind of tasks that must be completed one after another.

(Multiple Choice)
4.7/5
(31)

As you enter the start and finish times for tasks in the process of transforming a task list into a PERT/CPM chart, you move through the tasks, adding the task duration for each task to its start time to determine its finish time. As you move through the tasks, there are three important rules to keep in mind. What are they?

(Essay)
4.7/5
(47)

A project manager, or project leader, usually is a senior systems analyst or an IT department manager if the project is large.

(True/False)
4.8/5
(30)

In discussing PERT/CPM charts, you discuss the types of task patterns that can occur in a project schedule. You give an example of two tasks, A and B, that can both begin as soon as task C is finished. Which of the following is NOT a true statement about tasks A and B?

(Multiple Choice)
4.8/5
(33)

Project managers typically perform four main tasks. Identify these and explain what they are.

(Essay)
4.8/5
(41)

Most risk identifications include a brief description of all of the following EXCEPT ____.

(Multiple Choice)
4.9/5
(41)

A task is any work that requires the use of company resources including all of the following EXCEPT ____.

(Multiple Choice)
4.8/5
(41)

Which of the following is NOT a true statement about Gantt charts?

(Multiple Choice)