Exam 3: Managing Systems Projects
Exam 1: Introduction to Systems Analysis and Design112 Questions
Exam 2: Analyzing the Business Case112 Questions
Exam 3: Managing Systems Projects112 Questions
Exam 4: Requirements Modeling112 Questions
Exam 5: Data and Process Modeling112 Questions
Exam 6: Object Modeling112 Questions
Exam 7: Development Strategies112 Questions
Exam 8: User Interface Design112 Questions
Exam 9: Data Design112 Questions
Exam 10: System Architecture111 Questions
Exam 11: Managing Systems Implementation112 Questions
Exam 12: Managing Systems Support and Security112 Questions
Exam 13: Communication Tools45 Questions
Exam 14: CASE Tools44 Questions
Exam 15: Financial Analysis Tools44 Questions
Exam 16: Internet Resource Tools45 Questions
Select questions type
In Open Workbench, unlike in Microsoft Project, you create tasks and durations, indicate dependencies, and assign resources.
(True/False)
4.9/5
(39)
You begin by reviewing some of the key points of project planning. Which of the following is NOT a true statement about the process of developing a project plan?
(Multiple Choice)
4.9/5
(35)
In developing time and cost estimates, project managers must consider _____.
(Multiple Choice)
4.8/5
(36)
A ____ path includes all tasks that are vital to the project schedule.
(Multiple Choice)
4.8/5
(35)
Project scheduling involves all of the following EXCEPT ____.
(Multiple Choice)
4.9/5
(40)
-The accompanying figure shows task ____, which simplify a complex task by combining several activities.

(Multiple Choice)
4.9/5
(33)
-Over time, the distinctions between the Program Evaluation Review Technique (PERT) and the Critical Path Method (CPM) have disappeared, and today the scheduling technique is called ____________________, as represented in the accompanying figure.

(Short Answer)
4.7/5
(33)
Gantt charts often are included in progress reports to show project status graphically. _________________________
(True/False)
4.7/5
(36)
A risk ____ plan is a proactive effort to anticipate a risk and describe an action plan to deal with it.
(Multiple Choice)
4.8/5
(39)
In a PERT/CPM chart, each rectangular box, called a task box, has five sections that contain important information about a task.
(True/False)
4.7/5
(31)
MATCHING
Identify the letter of the choice that best matches the phrase or definition.
-The kind of task upon which other tasks depend.
(Multiple Choice)
4.9/5
(36)
Open Workbench can exchange files with Microsoft Project by importing and exporting the data in ____ file format.
(Multiple Choice)
4.9/5
(32)
If you do not have previous experience to measure a project in a given environment, you could design a prototype or pilot system to gain technical and cost estimating experience.
(True/False)
4.8/5
(34)
Project status meetings give project managers an opportunity to seek input and conduct brainstorming sessions.
(True/False)
4.9/5
(29)
Many project managers find ____ charts more helpful for scheduling, monitoring, and controlling projects.
(Multiple Choice)
4.9/5
(35)
In a PERT/CPM chart, each task has all of the following EXCEPT a(n) ____.