Exam 3: Managing the Information Systems Project
Exam 1: The Systems Development Environment174 Questions
Exam 2: The Origins of Software150 Questions
Exam 3: Managing the Information Systems Project167 Questions
Exam 4: Identifying and Selecting Systems Development Projects170 Questions
Exam 5: Initiating and Planning Systems Development Projects175 Questions
Exam 6: Determining System Requirements148 Questions
Exam 7: Structuring System Process Requirements236 Questions
Exam 8: Structuring System Data Requirements153 Questions
Exam 9: Designing Databases177 Questions
Exam 10: Designing Forms and Reports155 Questions
Exam 11: Designing Interfaces and Dialogues180 Questions
Exam 12: Designing Distributed and Internet Systems164 Questions
Exam 13: System Implementation166 Questions
Exam 14: Maintaining Information Systems160 Questions
Exam 15: Object-Oriented Analysis and Design: Use Cases51 Questions
Exam 16: Object-Oriented Analysis and Design: Activity Diagrams9 Questions
Exam 17: Objected-Oriented Analysis and Design: Object Modeling-Class Diagrams32 Questions
Exam 18: Object-Oriented Analysis and Design: Sequence Diagrams35 Questions
Select questions type
Match each of the following activities with its corresponding skills.
-Communication within and between teams,peer evaluations,conflict resolution,team building,self- management
(Multiple Choice)
5.0/5
(37)
Task identification structure refers to the process of dividing a project into manageable tasks and logically ordering them to ensure a smooth evolution between tasks.
(True/False)
4.8/5
(45)
Match each of the following project management phases with the activities associated with it.(Answers may occur more than once.)
-Shows the time overlap of activities.
(Multiple Choice)
4.8/5
(40)
A __________ is an online or hard-copy repository for all project correspondence,inputs,outputs,deliverables,procedures,and standards that is used for performing project audits,orienting new team members,communicating with management and customers,identifying future projects,and performing postproject reviews.
(Short Answer)
5.0/5
(44)
Critical path scheduling is a scheduling technique in which order and duration of a sequence of task activities directly affect the completion date of a project.
(True/False)
4.7/5
(46)
Project initiation is the second phase of the project management process,which focuses on defining clear,discrete activities and the work needed to complete each activity within a single project.
(True/False)
4.8/5
(39)
A logic model is a graphical representation of a project that shows each task as a horizontal bar whose length is proportional to its time for completion.
(True/False)
4.7/5
(33)
When a project manager works closely with customers to assure project deliverables meet expectations,he/she is performing a customer relations activity.
(True/False)
4.7/5
(39)
If an activity's optimistic time is 4 days,its realistic time is 10 days,and its pessimistic time is 25 days,then its estimated time would be 11.5 days.
(True/False)
4.9/5
(45)
Match each of the following project management phases with the activities associated with it.(Answers may occur more than once.)
-Monitor project progress against the baseline project plan
(Multiple Choice)
4.9/5
(37)
The focus of developing a communications plan activity is to collect and organize the tools that will be used while managing the project.
(True/False)
4.9/5
(34)
Match each of the following project management phases with the activities associated with it.(Answers may occur more than once.)
-Shows slack time available for each activity within activity rectangles.
(Multiple Choice)
4.9/5
(31)
Project planning is the first phase of the project management process in which activities are performed to assess the size,scope,and complexity of the project and to establish procedures to support later project activities.
(True/False)
4.8/5
(50)
Influencing the activities of others toward the attainment of a common goal through the use of intelligence,personality,and abilities refers to which of the following project manager activities?
(Multiple Choice)
4.7/5
(33)
__________ is the third phase of the project management process in which the plans created in the prior phases are put into action.
(Short Answer)
4.9/5
(28)
Match each of the following project management phases with the activities associated with it.(Answers may occur more than once.)
-Shows the sequence dependencies between activities.
(Multiple Choice)
4.8/5
(29)
If an activity's optimistic time is 3 months,its realistic time is 5 months,and its pessimistic time is 10 months,then its estimated time would be 5.5 months.
(True/False)
4.8/5
(30)
Determining the strengths and weaknesses of project deliverables,the processes used to create them,and the project management process is done during:
(Multiple Choice)
4.8/5
(35)
Gantt charts typically show how tasks must be ordered and when an activity should begin and end.
(True/False)
4.8/5
(40)