Exam 11: Learning Curves
Exam 1: Introduction to Operations Management80 Questions
Exam 2: Competitiveness, strategic Planning, and Productivity62 Questions
Exam 3: Demand Forecasting171 Questions
Exam 4: Product Design103 Questions
Exam 5: Reliability63 Questions
Exam 6: Strategic Capacity Planning75 Questions
Exam 7: Decision Analysis70 Questions
Exam 8: Process Design and Facility Layout169 Questions
Exam 9: Linear Programming98 Questions
Exam 10: Workjob Design147 Questions
Exam 11: Learning Curves67 Questions
Exam 12: Location Planning and Analysis69 Questions
Exam 13: the Transportation Model18 Questions
Exam 14: Management of Quality112 Questions
Exam 15: Statistical Quality Control132 Questions
Exam 16: Acceptance Sampling64 Questions
Exam 17: Supply Chain Management103 Questions
Exam 18: Inventory Management157 Questions
Exam 19: Aggregate Operations Planning and Master Scheduling73 Questions
Exam 20: Material Requirements Planning and Enterprise Resource Planning78 Questions
Exam 21: Just-In-Time and Lean Production89 Questions
Exam 22: Maintenance27 Questions
Exam 23: Job and Staff Scheduling116 Questions
Exam 24: Project Management131 Questions
Exam 25: Waiting-Line Analysis79 Questions
Exam 26: Simulation44 Questions
Select questions type
A learning percentage of 98% implies 2% learning.
Free
(True/False)
4.7/5
(38)
Correct Answer:
True
A manager wants to analyze the learning curve associated with producing one of his company's products.Accordingly,he has gathered the following data:
Approximately how long will it take to produce the tenth unit?

Free
(Multiple Choice)
4.8/5
(40)
Correct Answer:
C
The learning percentage can be determined from a learning curve table.
Free
(True/False)
4.7/5
(35)
Correct Answer:
False
A company is preparing a bid on a government contract for 40 units of a certain product.The operations manager estimates the assembly time required for the first two units to be 10.4 hours and 8.8 hours,respectively.What is the expected time required to produce the 40th unit?
(Multiple Choice)
4.8/5
(35)
Unit times for a job exhibit a learning effect.If the 2nd unit took 30 hours,and the 4th unit took 21 hours,roughly how many hours would you estimate the 3rd unit took?
(Multiple Choice)
4.8/5
(33)
Learning curves cannot be used if the labour time for the first unit is unknown.
(True/False)
4.9/5
(41)
If an 80% curve is appropriate for a task and the first unit takes ten hours,the average time for the first two units would be eight hours.
(True/False)
4.8/5
(43)
According to learning curve theory,for certain kinds of tasks the indirect labour time or cost per unit decreases as the number of units increases.
(True/False)
5.0/5
(38)
A job has an 80% learning curve.If the first unit took 40 hours to complete,the fourth unit should take roughly how many hours?
(Multiple Choice)
4.8/5
(38)
A 98% learning curve implies an exceptionally rapid rate of improvement.
(True/False)
4.9/5
(50)
A company is preparing a bid on a government contract for 40 units of a certain product.The operations manager estimates the assembly time required for the first two units to be 10.4 hours and 8.8 hours,respectively.What is the appropriate learning curve?
(Multiple Choice)
4.9/5
(36)
It took exactly 10 hours to produce the first widget on a 100 percent learning curve.The second widget will take how many hours to produce?
(Multiple Choice)
4.8/5
(43)
Developing work assignments in a job shop in a certain firm has a learning curve of 80 percent.If the second set of assignments takes 12 minutes,determine the length of time required for the following:
(i)the fifth set
(ii)sets 3,4,and 5 together
(Essay)
4.9/5
(28)
A company is preparing a bid on a government contract for 40 units of a certain product.The operations manager estimates the assembly time required for the first two units to be 10.4 hours and 8.8 hours,respectively.If the contract is cancelled after the first 20 units,approximately how much of the expected total direct labour will have been expended to that point?
(Multiple Choice)
4.8/5
(41)
Which of the following conveys the essence of learning curves?
(Multiple Choice)
4.9/5
(42)
A manager wants to analyze the learning curve associated with producing one of his company's products.Accordingly,he has gathered the following data:
How long did it take to produce the first unit?

(Multiple Choice)
4.8/5
(41)
The fact that human activities typically improve when they are done on a repetitive basis is described by a:
(Multiple Choice)
4.7/5
(35)
Learning curves can be used to understand how direct labour costs per unit can be expected to decrease as more units are produced.
(True/False)
4.8/5
(27)
Showing 1 - 20 of 67
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)