Exam 7: JIT/Lean production
Exam 1: Supply chain focused manufacturing planning and control30 Questions
Exam 2: Forecasting demand30 Questions
Exam 3: S&OP/Aggregate planning30 Questions
Exam 4: Master production schedule30 Questions
Exam 5: Supply chain focused inventory management27 Questions
Exam 6: MRP production system25 Questions
Exam 7: JIT/Lean production30 Questions
Exam 8: Push and pull production systems30 Questions
Exam 9: Capacity management30 Questions
Exam 10: Production planning and control for remanufacturing30 Questions
Exam 11: Supply chain focused outsourcing30 Questions
Exam 12: Manufacturing focused supply chain integration30 Questions
Select questions type
In your own words, explain why lean performs better than traditional remanufacturing in a paragraph.
(Essay)
4.8/5
(26)
The implementation of JIT moves beyond an adoption of a tool set.It is a organization wide philosophical change.One method of managing change is the Kotter's 8 Steps.Which of the following is not included in Kotter's 8 Steps as a step?
(Multiple Choice)
4.9/5
(30)
Provide a reason for why a JIT organization would end up with a smaller supplier base than other non-JIT ones.
(Short Answer)
4.9/5
(36)
Uniform Production is an element of JIT production which requires _________________ .Choose an option that does not fill in the blank correctly.
(Multiple Choice)
4.9/5
(31)
Briefly discuss the role of culture in regard to JIT using the US and Japan as examples.
(Essay)
4.7/5
(36)
Which of the following situations are likely to happen to the suppliers with implementation of JIT or lean?
1)The buyer will only use a limited number of suppliers
2)Most contracts will be based on long term goals
3)The suppliers are more likely to be subjected to reverse auctions
4)The focus of JIT relationships will be on reducing supplier power in the relationship
(Multiple Choice)
4.9/5
(33)
In your own words, briefly describe the concept of Uniform production utilized by JIT.
(Essay)
4.9/5
(34)
Among the following choices, select the ones that is closely associated with Just in time (JIT)philosophy.
1)SPC
2)MRP II
3)Concurrent problem solving
4)Push manufacturing
(Multiple Choice)
4.7/5
(44)
Which of the following is a correct paper kaizen guidelines?
(Multiple Choice)
4.8/5
(40)