Which of the following is a correct description of Capacity requirements planning (CRP)?

Free
(Multiple Choice)
4.9/5
(27)
Correct Answer:
Verified

B

Capacity is the measure of productive capability of a facility for a unit of time.Which of the following capacity types measures the company's total effective capacity under perfect conditions?

Free
(Multiple Choice)
4.9/5
(40)
Correct Answer:
Verified

A

_______________________________________________ is a major function of the capacity planning process named ____________.

Free
(Multiple Choice)
4.9/5
(26)
Correct Answer:
Verified

D

Define, in your words, capacity planning and control.

(Essay)
4.8/5
(28)

Dave is conducting Rough-Cut Capacity Planning (RCCP)for a product ATOR.The product ATOR' BOM has 2 levels.The assembly is at level 1.At level 2, there are component A, B and C.The Production Routings for product GTB is presented below.Using RCCR approach, find whether Work center 2 has enough capacity to produce 104 units of product ATOR.Work center 2's assigned capacity is 1,100 hours. Dave is conducting Rough-Cut Capacity Planning (RCCP)for a product ATOR.The product ATOR' BOM has 2 levels.The assembly is at level 1.At level 2, there are component A, B and C.The Production Routings for product GTB is presented below.Using RCCR approach, find whether Work center 2 has enough capacity to produce 104 units of product ATOR.Work center 2's assigned capacity is 1,100 hours.

(Essay)
4.8/5
(37)

Among the alternative RCCP approaches, name the approach that applies planning factors derived from historical data for the end item to MPS data and are used to estimate overall labor in order to estimate overall labor or machine hour capacity requirements.

(Multiple Choice)
4.9/5
(30)

Name the process of converting the master production schedule into requirements for key resources, including labor, machinery, warehouse capacity, suppliers' capabilities, and many other transformations.

(Essay)
4.8/5
(25)

Capacity planning is the creation of a series of interrelated hierarchical plans.The levels of these plans correlate with the levels of the manufacturing framework.Which of the following capacity plan and manufacturing process matches are at the same level? 1)Sales and Operations Planning <-->Rough-Cut Capacity Planning 2)Shop-Floor Control (SFC)<-->Rough-Cut Capacity Planning 3)Material Requirements Planning (MRP)<-->Capacity Requirements Planning 4)Master Production Scheduling (MPS)<-->Input/Output Analysis

(Multiple Choice)
4.9/5
(24)

AE Manufacturing has 60 machine hours every day.AE Manufacturing two products, A and B.When changing over from producing product B to A, there is no change over time.When changing over from producing product A to B, it takes 8 machine hours.If the previous day ended with producing product B, what is the effective capacity when AE Manufacturing has the following schedule: product A, product B, product A.

(Multiple Choice)
4.9/5
(32)

AMT Transportations operates 2 shifts per day with 25 drivers working during each shift.When each shift is 8 hours, what is the design capacity for a day?

(Short Answer)
4.9/5
(36)

Using RCOF and the information in the tables below, find the labor hour requirement for Work center 2 during period 2.The following is the distribution of the load across the WCs: \quad WC1(25%), \quad WC2(55%) \quad WC3(20%).  Using RCOF and the information in the tables below, find the labor hour requirement for Work center 2 during period 2.The following is the distribution of the load across the WCs:  \quad WC1(25%), \quad  WC2(55%) \quad WC3(20%).

(Short Answer)
4.8/5
(42)

Material Requirements Planning (MRP)operates on a component product level which is the level _____________ also operates at. 1)Component/Supplier Capacity Planning (SCP) 2)Sub-assembly/Input/Output Analysis 3)Raw material/Supply Chain Planning 4)Component/Resource Capacity Planning

(Multiple Choice)
4.8/5
(37)

There are 3 work stations (WC)with the following capacity: WC1 (2,000 units), WC2 (2,500 units), and WC3 (1,500 units).While the load could be shifted from WC1 to WC2 and also in the opposite direction, WC3's load cannot be shifted to other WCs as a result of specialized equipment.In the following load situation, what is not a good solution? WC1: 1500 units, WC2: 2250 units, WC3: 3100 units

(Multiple Choice)
5.0/5
(36)

Capacity is the measure of productive capability of a facility for a unit of time.Name the capacity measure that divides effective capacity with design capacity.

(Multiple Choice)
4.8/5
(36)

What is the planning horizon of the Capacity requirements planning (CRP)?

(Essay)
4.8/5
(41)

Of the following capacity planning horizons, which horizon is more concerned with capacity control over the next 4 weeks?

(Multiple Choice)
4.8/5
(34)

Dave is conducting Rough-Cut Capacity Planning (RCCP)for a product GTB.The product GTB' BOM has 2 levels.The assembly is at level 1.At level 2, there are component A and B.The Production Routings for product GTB is presented below.Using RCCR approach, find the Capacity Requirements for 4 units of product GTB. Dave is conducting Rough-Cut Capacity Planning (RCCP)for a product GTB.The product GTB' BOM has 2 levels.The assembly is at level 1.At level 2, there are component A and B.The Production Routings for product GTB is presented below.Using RCCR approach, find the Capacity Requirements for 4 units of product GTB.

(Multiple Choice)
4.8/5
(27)

Product gamma requires a sequence of 3 Work centers.The total output is 4000 units per period.What is the bottleneck? Explain whether the situation is plausible given the information.The following is the period production volume for each WC. WC1: 3500 units, \quad WC2: 5250 units, \quad WC3: 4100 units

(Essay)
4.8/5
(26)

Choose, among the following options, the inputs for Capacity requirements planning (CRP). 1)Loading capacity 2)Rescheduling data from MPS 3)Routing data 4)Planned and released order from MRP systems

(Multiple Choice)
4.8/5
(24)

Using RCOF and the information in the table below, find the labor hour requirement for Work center 1.The following is the distribution of the load across the WCs: WC1 (25%), \quad WC2 (55%), \quad WC3 (20%). Product A B C Labor hours 3 1 7 Units 10 5 6

(Multiple Choice)
4.8/5
(32)
Showing 1 - 20 of 30
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)