The amount of time an activity can be delayed without affecting the start time of any successor activity is known as free slack.

(True/False)
4.8/5
(32)

Which of the following terms is most closely associated with a task required by the project?

(Multiple Choice)
4.8/5
(32)

Milestones cannot be identified on a Gantt Chart.

(True/False)
4.8/5
(33)

Technical dependencies on a project plan are easiest to see on a:

(Multiple Choice)
4.9/5
(42)

Organ Bennett Inc., a public relations firm, is working on a project to improve the brand image of Sizil, a client firm, over a period of a year. The project requires Organ Bennett to organize a press conference to announce the launch of Sizil's new product. The project members need to invite reporters for the same. In the context of the language of the Program Evaluation and Review Technique (PERT) and the Critical Path Method (CPM), inviting reporters is most likely a(n) _____.

(Multiple Choice)
4.8/5
(31)

The actual project duration will be known with certainty after the project is completed.

(True/False)
4.8/5
(35)

The difference between LFT and EFT is called slack.

(True/False)
4.8/5
(39)