Exam 3: Planning the Project
Exam 1: The World of Project Management65 Questions
Exam 2: The Manager, the Organization, and the Team60 Questions
Exam 3: Planning the Project56 Questions
Exam 4: Budgeting the Project61 Questions
Exam 5: Scheduling the Project67 Questions
Exam 6: Allocating Resources to the Project70 Questions
Exam 7: Monitoring and Controlling the Project68 Questions
Exam 8: Evaluating and Terminating the Project71 Questions
Select questions type
According to the text, the use of sticky-notes can be particularly useful for constructing a(n)
Free
(Multiple Choice)
5.0/5
(33)
Correct Answer:
B
Taken together the RACI and the Work Breakdown Structure may be used to determine the importance of each task listed.
Free
(True/False)
4.9/5
(21)
Correct Answer:
False
The project plan should begin with a complete description of all agreements made with the client or any third party.
Free
(True/False)
4.9/5
(34)
Correct Answer:
False
The letters used in the RACI matrix help link a person and a task for accountability purposes.
(True/False)
4.9/5
(31)
A(n) __________________ shows the set of all tasks in a project arranged by task level?
(Multiple Choice)
4.8/5
(23)
The project baseline plan is the open, honest, and frequent communication between the interested parties of a project.
(True/False)
4.9/5
(44)
Mind mapping is a whole-brain approach that is particularly applicable to project management.
(True/False)
4.7/5
(39)
The manager of a project causes a catastrophic failure in the project that threatens the timely delivery of the project. Frank, another project manager, is asked to take over. He initiates a backup plan created by him, and he takes critical steps to recover from the setback and salvage the project. In this scenario, Frank is most likely using a(n) _____.
(Multiple Choice)
4.7/5
(30)
Which of the following is not a category in the RACI matrix?
(Multiple Choice)
5.0/5
(32)
What are some options for eliminating potential rework situations when they are discovered in the Design Structure Matrix?
(Essay)
4.8/5
(28)
A representative of senior management should be invited to the project launch meeting.
(True/False)
4.8/5
(34)
The primary purpose of the launch meeting is to develop the project plan and budget.
(True/False)
4.9/5
(37)
It is not possible to overdo it when it comes to project planning.
(True/False)
4.9/5
(40)
Which of the following is used to show linkages between people and tasks?
(Multiple Choice)
4.8/5
(31)
Showing 1 - 20 of 56
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)