Exam 3: Planning the Project
Exam 1: The World of Project Management65 Questions
Exam 2: The Manager, the Organization, and the Team60 Questions
Exam 3: Planning the Project56 Questions
Exam 4: Budgeting the Project61 Questions
Exam 5: Scheduling the Project67 Questions
Exam 6: Allocating Resources to the Project70 Questions
Exam 7: Monitoring and Controlling the Project68 Questions
Exam 8: Evaluating and Terminating the Project71 Questions
Select questions type
The salary requirements of human resources are a required element in the project plan.
(True/False)
5.0/5
(35)
Renee, a project manager, is responsible for developing a project plan for her new project. To do so, she needs to consider all the tasks that would need to be done to produce the deliverable and make a list of them. In this scenario, Renee needs to prepare a(n) _____ for the project.
(Multiple Choice)
4.9/5
(31)
Roger is a scientist who is developing a new drug to cure cancer. He lists five possible ways in which the drug might fail. He ranks the severity of the consequences of each failure, the likelihood of each failure's occurrence, and the ease of detection of each failure on a scale of 1 to 10. In the context of Failure Mode and Effect Analysis, which of the following failures has the highest Risk Priority Number (RPN)?
(Multiple Choice)
4.8/5
(42)
Which of the following is most closely associated with FMEA?
(Multiple Choice)
4.8/5
(34)
What is the primary purpose of creating a work breakdown structure?
(Multiple Choice)
4.9/5
(43)
Entries above the diagonal in the Design Structure Matrix indicate
(Multiple Choice)
4.8/5
(30)
Suzanne, a human resources manager in an event management company, is assigned the task of arranging a farewell dinner for the CEO of the company. She uses Microsoft Project (MSP) to create a work breakdown structure list for this task. The MSP creates a list of Level 1 tasks, Level 2 tasks, and so on. Suzanne then adds appropriate descriptions to each task. While doing so, Suzanne should ensure that:
(Multiple Choice)
4.9/5
(35)
Duncan, a project manager, has to create a work breakdown structure (WBS) for a new project. He gathers the project team and provides them with a pad of sticky-notes. After defining the project objectives and the major activities that would need to be done to achieve those objectives, he asks his team members to write all the tasks that they think would be required to complete the project on the sticky-notes. These notes are then stuck on a wall in a sequential manner. In this scenario, Duncan uses a(n) _____ to create the WBS.
(Multiple Choice)
4.9/5
(37)
A limitation of traditional project management planning tools is that they do not address the flow of information.
(True/False)
4.8/5
(45)
The design structure matrix can be used to identify potential rework situations due to the flow of information in a project.
(True/False)
4.9/5
(35)
Predecessors must be listed in the WBS because they are critical for scheduling.
(True/False)
4.8/5
(36)
The start and finish date of a project must be specified before the action plan can be completed.
(True/False)
4.8/5
(38)
Showing 21 - 40 of 56
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)