Exam 16: Management Control Systems
Exam 1: Introduction to Management Accounting35 Questions
Exam 2: An Introduction to Cost Terms and Concepts65 Questions
Exam 3: Cost Assignment52 Questions
Exam 4: Accounting Entries for a Job Costing System25 Questions
Exam 5: Process Costing56 Questions
Exam 6: Joint and By-Product Costing65 Questions
Exam 7: Income Effects of Alternative Cost Accumulation Systems42 Questions
Exam 8: Cost-Volume-Profit Analysis59 Questions
Exam 9: Measuring Relevant Costs and Revenues for Decision-Making77 Questions
Exam 10: Activity-Based Costing40 Questions
Exam 11: Activity-Based Costing56 Questions
Exam 12: Decision-Making Under Conditions of Risk and Uncertainty15 Questions
Exam 13: Capital Investment Decisions: Appraisal Methods60 Questions
Exam 14: Capital Investment Decisions: the Impact of Capital Rationing, Taxation, Inflation and Risk22 Questions
Exam 15: The Budgeting Process76 Questions
Exam 16: Management Control Systems60 Questions
Exam 17: Standard Costing and Variance Analysis 181 Questions
Exam 18: Standard Costing and Variance Analysis 2: Further Aspects12 Questions
Exam 19: Divisional Financial Performance Measures48 Questions
Exam 20: Transfer Pricing in Divisionalized Companies43 Questions
Exam 21: Strategic Cost Management101 Questions
Exam 22: Strategic Performance Management29 Questions
Exam 23: Cost Estimation and Cost Behaviour59 Questions
Exam 24: Quantitative Models for the Planning and Control of Inventories40 Questions
Exam 25: The Application of Linear Programming to Management Accounting30 Questions
Select questions type
Which of the following is NOT a potential disadvantage of participative budgeting?
Free
(Multiple Choice)
4.8/5
(37)
Correct Answer:
B
Figure 16-1
Armati, SA., is looking for feedback on company performance. The company compares the budget for the year with the actual costs. Data have been collected below:
Armati, SA., had the following budgeted data: Unit sales for 2011 26,000 Unit production for 2011 26,000 Budgeted fixed overhead for 2011 : Supervision £800 Depreciation 2,000 Rent 100 Budgeted variable costs per unit: Direct materials £0.15 Direct labour 0.20 Supplies 0.02 Indirect labour 0.05 Power 0.02 The following actually occurred: Actual unit sales for 2011 24,000 Actual unit production for 2011 28,000 Actual fixed overhead for 2011 : Supervision £850 Depreciation 2,000 Rent 100 Actual variable costs: Direct materials £3,500 Direct labour 4,900 Supplies 530 Indirect labour 1,250 Power 470
-Refer to Figure 16-1. The static budget variance for supplies is
Free
(Multiple Choice)
4.9/5
(44)
Correct Answer:
A
Figure 16-1
Armati, SA., is looking for feedback on company performance. The company compares the budget for the year with the actual costs. Data have been collected below:
Armati, SA., had the following budgeted data: Unit sales for 2011 26,000 Unit production for 2011 26,000 Budgeted fixed overhead for 2011 : Supervision £800 Depreciation 2,000 Rent 100 Budgeted variable costs per unit: Direct materials £0.15 Direct labour 0.20 Supplies 0.02 Indirect labour 0.05 Power 0.02 The following actually occurred: Actual unit sales for 2011 24,000 Actual unit production for 2011 28,000 Actual fixed overhead for 2011 : Supervision £850 Depreciation 2,000 Rent 100 Actual variable costs: Direct materials £3,500 Direct labour 4,900 Supplies 530 Indirect labour 1,250 Power 470
-Refer to Figure 16-1. The static budget variance for total fixed overhead is
Free
(Multiple Choice)
4.9/5
(39)
Correct Answer:
A
The static budget variance for materials is £200 F and the budgeted cost for materials is £52,000. If the budgeted volume is 13,000 and the actual volume is 13,500, then the flexible budget variance is
(Multiple Choice)
4.7/5
(41)
Figure 16-1
Armati, SA., is looking for feedback on company performance. The company compares the budget for the year with the actual costs. Data have been collected below:
Armati, SA., had the following budgeted data: Unit sales for 2011 26,000 Unit production for 2011 26,000 Budgeted fixed overhead for 2011 : Supervision £800 Depreciation 2,000 Rent 100 Budgeted variable costs per unit: Direct materials £0.15 Direct labour 0.20 Supplies 0.02 Indirect labour 0.05 Power 0.02 The following actually occurred: Actual unit sales for 2011 24,000 Actual unit production for 2011 28,000 Actual fixed overhead for 2011 : Supervision £850 Depreciation 2,000 Rent 100 Actual variable costs: Direct materials £3,500 Direct labour 4,900 Supplies 530 Indirect labour 1,250 Power 470
-Refer to Figure 16-1. The static budget variance for direct materials is
(Multiple Choice)
5.0/5
(41)
Figure 16-1
Armati, SA., is looking for feedback on company performance. The company compares the budget for the year with the actual costs. Data have been collected below:
Armati, SA., had the following budgeted data: Unit sales for 2011 26,000 Unit production for 2011 26,000 Budgeted fixed overhead for 2011 : Supervision £800 Depreciation 2,000 Rent 100 Budgeted variable costs per unit: Direct materials £0.15 Direct labour 0.20 Supplies 0.02 Indirect labour 0.05 Power 0.02 The following actually occurred: Actual unit sales for 2011 24,000 Actual unit production for 2011 28,000 Actual fixed overhead for 2011 : Supervision £850 Depreciation 2,000 Rent 100 Actual variable costs: Direct materials £3,500 Direct labour 4,900 Supplies 530 Indirect labour 1,250 Power 470
-Refer to Figure 16-1. The static budget variance for rent is
(Multiple Choice)
4.9/5
(40)
Which of the following is NOT an advantage of participative budgeting?
(Multiple Choice)
4.8/5
(41)
Figure 16-1
Armati, SA., is looking for feedback on company performance. The company compares the budget for the year with the actual costs. Data have been collected below:
Armati, SA., had the following budgeted data: Unit sales for 2011 26,000 Unit production for 2011 26,000 Budgeted fixed overhead for 2011 : Supervision £800 Depreciation 2,000 Rent 100 Budgeted variable costs per unit: Direct materials £0.15 Direct labour 0.20 Supplies 0.02 Indirect labour 0.05 Power 0.02 The following actually occurred: Actual unit sales for 2011 24,000 Actual unit production for 2011 28,000 Actual fixed overhead for 2011 : Supervision £850 Depreciation 2,000 Rent 100 Actual variable costs: Direct materials £3,500 Direct labour 4,900 Supplies 530 Indirect labour 1,250 Power 470
-Refer to Figure 16-1. The flexible budget for direct materials cost in 2011 is
(Multiple Choice)
4.8/5
(41)
If production was budgeted at 400 units and the actual production was 420 units, what would be the flexible budget variance for materials if the actual cost of materials was £4,150 and the budgeted cost per unit is £10?
(Multiple Choice)
4.9/5
(32)
Figure 16-3
Harald, SA., has done a cost analysis for its production of bumper stickers. The following activities and cost drivers have been developed: Activity Cost Formula Maintenance £11,000+£0.11 per machine hour Machining £25,000+£0.50 per machine hour Setups £50 per batch Purchasing £200+£45 per purchase order Following are the actual costs of producing 85,000 stickers: 5,000 machine hours; 10 batches; 20 purchase orders Maintenance £11,500 Machining 28,300 Setups 550 Purchasing 1,000
-Refer to Figure 16-3. What is the budget variance for setups in an activity-based performance report?
(Multiple Choice)
4.8/5
(36)
Which of the following departments would NOT be classified as a profit centre?
(Multiple Choice)
4.9/5
(41)
Which of the following facets of a responsibility accounting system is most likely to lead employees to distrust the entire budgeting and performance evaluation system?
(Multiple Choice)
4.8/5
(35)
Figure 16-2
Glenn, SA., has done a cost analysis for its production of T-shirts. The following activities and cost drivers have been developed: Activity Cost Formula Maintenance £11,000+£2 per machine hour Machining £55,000+£3 per machine hour Inspection £70,000+£500 per batch Setups £2,000 per batch Purchasing £80,000+£150 per purchase order Following are the actual costs of producing 75,000 T-shirts: 5,000 machine hours; 10 batches; 20 purchase orders Maintenance £20,000 Machining 73,000 Inspection 73,000 Setups 18,000 Purchasing 82,000
-Refer to Figure 16-2. What is the budget variance for purchasing in an activity-based performance report?
(Multiple Choice)
4.9/5
(26)
If production was budgeted at 400 units and the actual production was 420 units, what would be the static budget variance for materials if the actual cost of materials was £4,150 and the budgeted cost per unit is £10?
(Multiple Choice)
4.7/5
(37)
Figure 16-5
Torino, SA., manufactures machine parts. Torino has developed a static budget for its plant at an activity level of 10,000 direct labour hours for the month of March. The actual level of activity was 11,000 hours. The following table summarizes the static budget and the actual costs for March: Static Budget Actual Costs (10,000) (11,000) Variance Variable costs £21,000 £22,000 £1,000 Fixed costs 7,800 7,700 100 Total £28,800 £29,700 £900
-Refer to Figure 16-5. What is the flexible budget for March?
(Multiple Choice)
4.8/5
(32)
Figure 16-4
Villafane, SA., has done a cost analysis for its production of decals. The following activities and cost drivers have been developed: Activity Cost Formula Design £5,000+£0.05 per machine hour Machining £25,000+£0.01 per machine hour Setups £35 per batch Purchasing £50+£15 per purchase order Following are the actual costs of producing 35,000 decals: 1,000 machine hours; 5 batches; 30 purchase orders Design £5,080 Machining ? Setups ? Purchasing £600 The following variances were given in the activity performance report: Design ? Machining £40 Setups £15 Purchasing ?
-Refer to Figure 16-4. What is the activity variance for design?
(Multiple Choice)
4.9/5
(41)
Which of the following must be addressed if budgets are to be used in performance evaluation?
(Multiple Choice)
4.7/5
(50)
Participative budgeting offers which of the following advantages?
(Multiple Choice)
4.8/5
(34)
Showing 1 - 20 of 60
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)