Exam 17: Standard Costing and Variance Analysis 1

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Labour rate variances can be the result of

Free
(Multiple Choice)
4.7/5
(34)
Correct Answer:
Verified

D

Figure 17-3 Tuvok Ltd. has developed the following standards for one of its products: Standard cost of materials £0.50 per pound Materials purchased and used 20,000 pounds Total paid to suppliers £11,000 Standard quantity allowed 18,000 pounds -Refer to Figure 17-3. Tuvok's materials usage variance is

Free
(Multiple Choice)
4.8/5
(32)
Correct Answer:
Verified

A

A favourable materials price variance may be caused by

Free
(Multiple Choice)
4.7/5
(26)
Correct Answer:
Verified

B

If variable overhead is applied based on direct labour hours and there is an unfavourable labour efficiency variance,

(Multiple Choice)
4.9/5
(34)

Taylor Company's budgeted sales were 10,000 units at £200 per unit. Actual sales were 9,200 units at £210 per unit. Taylor's sales price variance is

(Multiple Choice)
4.8/5
(47)

Figure 17-8 The following information was extracted from the accounting records of Noelle Company: STANDARD COST CARD PER UNIT Direct materials: 8 pounds \times£1.20 per pound £9.60 Direct labour: 3 hours \times£20 per hour 60.00 Variable overhead: 3 hours \times£6 per hour 18.00 Fixed overhead ? Total standard cost per unit ? Budgeted fixed overhead for the period is £420,000, and the budgeted fixed overhead rate is based on an expected capacity of 30,000 direct labour hours. The following information is available regarding the company's operations for the period: Units produced 10,500 Direct labour 29,000 hours costing £590,000 Overhead incurred: £182,000 Variable £430,000 -Refer to Figure 17-8. Noelle's fixed overhead spending variance would be

(Multiple Choice)
4.8/5
(27)

A sales volume variance will be favourable when:

(Multiple Choice)
4.7/5
(35)

Variances indicate

(Multiple Choice)
4.8/5
(33)

Figure 17-8 The following information was extracted from the accounting records of Noelle Company: STANDARD COST CARD PER UNIT Direct materials: 8 pounds \times£1.20 per pound £9.60 Direct labour: 3 hours \times£20 per hour 60.00 Variable overhead: 3 hours \times£6 per hour 18.00 Fixed overhead ? Total standard cost per unit ? Budgeted fixed overhead for the period is £420,000, and the budgeted fixed overhead rate is based on an expected capacity of 30,000 direct labour hours. The following information is available regarding the company's operations for the period: Units produced 10,500 Direct labour 29,000 hours costing £590,000 Overhead incurred: £182,000 Variable £430,000 -Refer to Figure 17-8. Noelle's standard fixed overhead rate is

(Multiple Choice)
4.8/5
(30)

Figure 17-5 Ebola Company has developed the following standards for one of its products: Direct materials 20 pounds \times£4 per pound Direct labour 5 hours \times£18 per hour Variable overhead 5 hours \times£4 per hour The following activities occurred during the month of October: Materials purchased 230,000 pounds at £4.20 per pound Materials used 220,000 pounds Units produced 10,000 units Direct labour 51,000 hours at £17.70 per hour Actual variable overhead £240,000 The company records materials price variances at the time of purchase. -Refer to Figure 17-5. Ebola's labour rate variance would be

(Multiple Choice)
4.9/5
(32)

The two variances for variable overhead are

(Multiple Choice)
4.8/5
(32)

An unfavourable materials price variance with a favourable materials usage variance would most likely be the result of

(Multiple Choice)
4.7/5
(35)

Figure 17-7 Orient Company has developed the following standards for one of its products: Direct materials 10 pounds \times£8 per pound Direct labour 6 hours \times£20 per hour Variable overhead 6 hours \times£6 per hour The following activities occurred during the month of November: Materials purchased 8,000 pounds costing £70,000 Materials used 6,500 pounds Units produced 600 units Direct labour 4,200 hours costing £75,600 Actual variable overhead £26,400 The company records materials price variances at the time of purchase. -Refer to Figure 17-7. Orient's labour rate variance would be

(Multiple Choice)
4.7/5
(43)

Figure 17-2 Rax Company has developed the following standards for one of its products: Direct materials 12 pounds * £14 per pound Direct labour 3 hours * £18 per hour Variable overhead 3 hours * £8 per hour The following activities occurred during the month of October: Materials purchased 10,000 pounds at £13.60 per pound Materials used 9,000 pounds Units produced 800 units Direct labour 2,500 hours at £19.00 per hour Actual variable overhead £22,000 The company records materials price variances at the time of purchase. -Refer to Figure 17-2. Rax's variable standard cost per unit would be

(Multiple Choice)
5.0/5
(44)

If actual fixed overhead was £120,000 and there was a £2,600 favourable spending variance and a £2,000 unfavourable volume variance, budgeted fixed overhead must have been

(Multiple Choice)
4.8/5
(31)

Figure 17-4 Shannon Ltd.'s standard cost card contained the following information: Direct labour: 1.25 hours * £8.00 per hour = £10.00 Shannon planned to make 12,000 units. Shannon actually made 10,000 units using 13,000 hours. -Refer to Figure 17-4. Shannon's labour efficiency variance was

(Multiple Choice)
4.9/5
(42)

Figure 17-8 The following information was extracted from the accounting records of Noelle Company: STANDARD COST CARD PER UNIT Direct materials: 8 pounds \times£1.20 per pound £9.60 Direct labour: 3 hours \times£20 per hour 60.00 Variable overhead: 3 hours \times£6 per hour 18.00 Fixed overhead ? Total standard cost per unit ? Budgeted fixed overhead for the period is £420,000, and the budgeted fixed overhead rate is based on an expected capacity of 30,000 direct labour hours. The following information is available regarding the company's operations for the period: Units produced 10,500 Direct labour 29,000 hours costing £590,000 Overhead incurred: £182,000 Variable £430,000 -Refer to Figure 17-8. Noelle's variable overhead efficiency variance would be

(Multiple Choice)
4.8/5
(34)

Fixed overhead was budgeted at £500,000 and 25,000 direct labour hours were budgeted. If the fixed overhead volume variance was £12,000 favourable and the fixed overhead spending variance was £16,000 unfavourable, fixed overhead applied must be

(Multiple Choice)
4.8/5
(45)

An unfavourable materials usage variance may be caused by

(Multiple Choice)
4.8/5
(29)

Figure 17-5 Ebola Company has developed the following standards for one of its products: Direct materials 20 pounds \times£4 per pound Direct labour 5 hours \times£18 per hour Variable overhead 5 hours \times£4 per hour The following activities occurred during the month of October: Materials purchased 230,000 pounds at £4.20 per pound Materials used 220,000 pounds Units produced 10,000 units Direct labour 51,000 hours at £17.70 per hour Actual variable overhead £240,000 The company records materials price variances at the time of purchase. -Refer to Figure 17-5. Ebola's labour efficiency variance would be

(Multiple Choice)
4.7/5
(29)
Showing 1 - 20 of 81
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)