Exam 9: Project Scheduling: Pertcpm

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

To determine how to crash activity times

(Multiple Choice)
4.9/5
(36)

For an activity with more than one immediate successor activity, its latest-finish time is equal to the

(Multiple Choice)
4.9/5
(36)

Crashing refers to an unanticipated delay in a critical path activity that causes the total time to exceed its limit.

(True/False)
4.8/5
(27)

The critical path

(Multiple Choice)
4.8/5
(35)

The project manager should monitor the progress of any activity with a large time variance even if the expected time does not identify the activity as a critical activity.

(True/False)
4.9/5
(42)

When activity times are uncertain, total project time is normally distributed with mean equal to the sum of the means of all of the critical activities.

(True/False)
4.8/5
(28)

The variance in the project completion time is the sum of the variances of all activities in the project.

(True/False)
4.9/5
(35)

The earliest start time rule

(Multiple Choice)
4.9/5
(43)

A path through a project network must reach every node.

(True/False)
4.7/5
(31)

For an activity with more than one immediate predecessor activity, which of the following is used to compute its earliest finish (EF) time?

(Multiple Choice)
4.7/5
(18)

Constraints in the LP models for crashing decisions are required to compare the activity's earliest finish time with the earliest finish time of each predecessor.

(True/False)
4.8/5
(36)

The earliest start time for an activity is equal to the smallest of the earliest finish times for all its immediate predecessors.

(True/False)
4.9/5
(38)
Showing 21 - 32 of 32
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)