Exam 5: Project Definition: Creating the Using the Work Breakdown Structure
Exam 1: Managing Projects: What and Why12 Questions
Exam 2: The Effective Project Manager14 Questions
Exam 3: Project Selection: Doing the Right Thing14 Questions
Exam 4: Project Initiation: Setting the Stage for Action12 Questions
Exam 5: Project Definition: Creating the Using the Work Breakdown Structure13 Questions
Exam 6: Assessing and Preparing for Project Uncertainties14 Questions
Exam 7: Project Scheduling: Adding the Time Dimension21 Questions
Exam 8: Modifying Project Schedules to Accommodate Time and Resource Constraints18 Questions
Exam 9: Monitoring and Controlling Project Performance16 Questions
Exam 10: Finishing Well: Project Closure and Learning12 Questions
Select questions type
Which of the following WBS formats is are) best generated during a brainstorming session?
Free
(Multiple Choice)
4.8/5
(32)
Correct Answer:
A
A national circus organization performs in outdoor locations in approximately 35 cities each year. The same technical crew is used to set up and take down rides for all locations. Given that the set up for the rides is exactly the same at each location, and set up at the first location for a particular ride takes 85 minutes, how long would the set up for the same ride take at the 8th location? Assume a 75 percent learning rate and round to two places to the right of the decimal.
Free
(Multiple Choice)
4.9/5
(36)
Correct Answer:
B
Your school's recruiting staff is planning a multi-country road trip to Africa and the Middle East. Staff members will visit eight cities over a two-week period, and will set up an elaborate display, booth, and audio-visual show in each city. They have been reviewing last year's tour and discovered some information about how long the setup was in the same cities. Unfortunately, they do not have data for all cities. The data they do have are displayed below:
City (in order of visit) Time Required for Setup Last Year (1) Lagos 14 hours (2) Casablanca Unknown (3) Khartoum 8.876 hours (4) Nairobi 7.875 hours
It is possible to solve this problem without a leaming curve table, but we advise the instructor to include one at the end of the exam for those students who would like to use it.
What rate of learning can the team estimate from the available data? round to the nearest whole number)
Free
(Multiple Choice)
4.9/5
(26)
Correct Answer:
D
An easy way to assess team member interest in various aspects of a project before assigning responsibility is:
(Multiple Choice)
4.9/5
(35)
A project team is using the PERT method to estimate time durations for tasks. One of the tasks has the following parameters:
to = 25 days
tp = 50 days
tm = 30 days
Based on these parameters, expected time for this task would be:
(Multiple Choice)
4.9/5
(36)
A new project manager is taking over his company's annual charity event. Several members of the team have worked on this event project in previous years. In generating a time estimation for the various tasks, which of the following is are) most likely to aid improve estimation accuracy?
(Multiple Choice)
4.8/5
(41)
All of the following are advantages to including the team in creating the WBS, EXCEPT:
(Multiple Choice)
4.8/5
(32)
Which of the following is not a characteristic of mind mapping as a tool for WBS development?
(Multiple Choice)
4.8/5
(34)
Which WBS approach is most likely to leave team members with individual views of the work packages, but not an entire view of the project?
(Multiple Choice)
4.8/5
(38)
A consumer electronics company is planning a 16-city product show in Central and South America. The 25 crewmembers have committed to working the entire tour. Set-up time in the first city, Managua, is estimated to require 200 hours of calendar time, and based on historical data, the project manager is forecasting a learning rate of 85%. Based on learning curve concepts, what is the estimate for the time needed to set up in the 16th city, Caracas? Figures rounded to 2 places to the right of decimal.)
(Multiple Choice)
4.9/5
(32)
Which of the following is a reasonable way to determine the learning rate for a project?
(Multiple Choice)
4.8/5
(27)
Which of these is the best guideline for determining how far a team should go in breaking down the WBS?