Exam 9: Monitoring and Controlling Project Performance
Exam 1: Managing Projects: What and Why12 Questions
Exam 2: The Effective Project Manager14 Questions
Exam 3: Project Selection: Doing the Right Thing14 Questions
Exam 4: Project Initiation: Setting the Stage for Action12 Questions
Exam 5: Project Definition: Creating the Using the Work Breakdown Structure13 Questions
Exam 6: Assessing and Preparing for Project Uncertainties14 Questions
Exam 7: Project Scheduling: Adding the Time Dimension21 Questions
Exam 8: Modifying Project Schedules to Accommodate Time and Resource Constraints18 Questions
Exam 9: Monitoring and Controlling Project Performance16 Questions
Exam 10: Finishing Well: Project Closure and Learning12 Questions
Select questions type
Consider the following project circumstances. Assume the information is accurate.
PV = $5,000,000
EV = $9,000,000
AC = $12,000,000
BAC = $15,000,000
Estimated Duration = 24 months
Elapsed Time To Date = 15 months
The project sponsor has called the PM into her office and asked the PM to resolve the most serious problem represented by the data shown above. Which of these options would be most appropriate and important for the PM to consider first in following the sponsor's request?
Free
(Multiple Choice)
4.8/5
(41)
Correct Answer:
E
A project team has worked for six months on a solar power project that will involve an entirely new technology. Early in the project, they chose a very specific approach from among several available, and they have continued pursuing this approach in spite of repeated failures. The project sponsor has warned them the project will be cancelled if they do not achieve success within one month. The team decides to stick with the current approach and work harder rather than experimenting with an alternative technology option. Which phenomenon best describes what has influenced the team's decision?
Free
(Multiple Choice)
4.9/5
(33)
Correct Answer:
E
Given the following information about a project portfolio, what would be the most likely outcome associated with taking 10% of the resources from project A and giving them to project B? Assume the axis of the graph is the point where both CPI and SPI are equal to 1.

Free
(Multiple Choice)
4.8/5
(36)
Correct Answer:
D
Given the following information at week 19 of a 57-week project:
PV = 1,200 hours
EV = 1,400 hours
AC = 1,000 hours
Schedule variance percent SV%) and cost variance percent CV%), respectively, would be:
(Multiple Choice)
4.8/5
(40)
Which of the following is important to consider when choosing metrics to monitor project performance?
(Multiple Choice)
4.9/5
(40)
Given the following information at week 12 of a 54-week project:
PV = 1,200 hours
EV = 1,400 hours
AC = 1,000 hours
Schedule variance percent SV%) and cost variance percent CV%), respectively, would be:
(Multiple Choice)
4.8/5
(29)
A project task is scheduled to begin on Monday and is estimated to require five days of full-time work for the assigned team member, Chauncey. He has delayed beginning any work on the task until Thursday afternoon and believes he can finish by the end of the day Friday. Which of the following phenomena best describes what has influenced Chauncey's behavior?
(Multiple Choice)
4.9/5
(36)
What is the difference between planned value PV) and earned value EV)?
(Multiple Choice)
4.8/5
(30)
Given the following information about a project:
EV = $20,000
PV = $15,000
AC = $25,000
BAC = $40,000
Estimated Duration = 6 months
Assuming this is the only information available, which of these can we legitimately conclude about the project?
(Multiple Choice)
4.9/5
(33)
Given the following information about a project:
EV = $1,000,000
PV = $2,000,000
AC = $3,000,000
BAC = $4,000,000
What can we legitimately say about this project if this is the only information we have?
(Multiple Choice)
4.7/5
(27)
Which of the following is/are sources of influence that can cause actual project performance to differ from planned performance?
(Multiple Choice)
4.9/5
(32)
Review the following schedule for a small project involving only two activities:
At the end of week two, progress information for Tasks A and B is as follows:
PV AC \% Complete A \ 2,000 \ 1,000 50\% B \ 2,000 \ 3,000 50\%
What can we conclude about the project at the end of week two?

(Multiple Choice)
4.8/5
(36)
What are possible values for earned value EV), planned value PV), and actual cost AC) if a project has an SPI of 0.5 and a CPI of 2.0?
(Multiple Choice)
5.0/5
(27)
Which of the following project monitoring tools would be most appropriate to use for a large, highly complex project such as the design and construction of a space station?
(Multiple Choice)
4.7/5
(33)
Which of the following offers the best advice for an organization that wishes to implement a project monitoring system for large scale, multi-year projects?
(Multiple Choice)
4.8/5
(33)
Given the following information about a project portfolio, what would be the most likely outcome associated with taking 10% of the resources from project A and giving them to project B? Assume the vertical and horizontal axes of the graph are the points where CPI and SPI are equal to 1.

(Multiple Choice)
4.8/5
(29)
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)