Exam 8: Modifying Project Schedules to Accommodate Time and Resource Constraints
Exam 1: Managing Projects: What and Why12 Questions
Exam 2: The Effective Project Manager14 Questions
Exam 3: Project Selection: Doing the Right Thing14 Questions
Exam 4: Project Initiation: Setting the Stage for Action12 Questions
Exam 5: Project Definition: Creating the Using the Work Breakdown Structure13 Questions
Exam 6: Assessing and Preparing for Project Uncertainties14 Questions
Exam 7: Project Scheduling: Adding the Time Dimension21 Questions
Exam 8: Modifying Project Schedules to Accommodate Time and Resource Constraints18 Questions
Exam 9: Monitoring and Controlling Project Performance16 Questions
Exam 10: Finishing Well: Project Closure and Learning12 Questions
Select questions type
Which of the following characteristics would make an activity an unattractive candidate for crashing?
Free
(Multiple Choice)
4.8/5
(41)
Correct Answer:
C
In evaluating time-cost tradeoffs, we start by crashing the activity on the critical path that:
Free
(Multiple Choice)
4.8/5
(32)
Correct Answer:
A
What is the critical chain in the schedule below?

Free
(Multiple Choice)
4.8/5
(36)
Correct Answer:
D
The next three questions relate to the following scenario: Erica is planning a large surprise party for her best friend. She has developed the plan below which includes estimates of the time in hours) and cost necessary to perform each of the activities required.
Activity Predeces sor Normal Time (hrs) Crash Time (hrs) Norm al Cost Crash Cost A. Create Guest List -- 8 4 \ 200 \ 310 B. Send Invitations A 2 1 \ 125 \ 150 C. Plan Decorations A 8 6 \ 300 \ 370 D. Plan Menu A 3 2 \ 150 \ 210 E. Shop D 4 2 \ 475 \ 550 F. Prepare Food E 5 3 \ 225 \ 475
-To reduce the time for Activity F, Prepare Food, Erica can purchase some of the food from a caterer rather than cook it herself. As shown in the table above, this can reduce the time for Activity F by one or two hours, depending on how much catered food she purchases. What is the crash cost per hour for this activity?
(Multiple Choice)
4.8/5
(41)
Ganesh has been asked to create a project team for a major web development effort. He and the project sponsor have discussed team size and they are debating two options:
-Perform the project in 12 months with a team of 15 people
-Crash the project and complete it in 6 months with a team of 34 people
Which of the following will be true about the contrast between these two options?
(Multiple Choice)
4.9/5
(33)
Using the following figures, what is the incremental crash cost for this project activity?
Normal time = 6 months, Crash time = 4 months
Normal cost = $27,000, Crash cost = $35,000
(Multiple Choice)
4.9/5
(31)
The next three questions relate to the following scenario: Erica is planning a large surprise party for her best friend. She has developed the plan below which includes estimates of the time in hours) and cost necessary to perform each of the activities required.
Activity Predeces sor Normal Time (hrs) Crash Time (hrs) Norm al Cost Crash Cost A. Create Guest List -- 8 4 \ 200 \ 310 B. Send Invitations A 2 1 \ 125 \ 150 C. Plan Decorations A 8 6 \ 300 \ 370 D. Plan Menu A 3 2 \ 150 \ 210 E. Shop D 4 2 \ 475 \ 550 F. Prepare Food E 5 3 \ 225 \ 475
-Erica's internet-based business pays her about $40 per hour. Therefore, for every hour she works on this party project, she will experience a lost opportunity cost of $40. She would initially like to test the idea of reducing project duration by one hour. Which activity should she crash first?
(Multiple Choice)
4.8/5
(28)
Which of the following is most associated with fast tracking?
(Multiple Choice)
4.8/5
(32)
The next three questions are related to the project schedule shown below, which has been adjusted to accommodate resource constraints.
-In the network shown above, given the current placement of float, where would a feeding buffer be most appropriate from among the options below?

(Multiple Choice)
4.9/5
(39)
The next three questions relate to the following scenario: Erica is planning a large surprise party for her best friend. She has developed the plan below which includes estimates of the time in hours) and cost necessary to perform each of the activities required.
Activity Predeces sor Normal Time (hrs) Crash Time (hrs) Norm al Cost Crash Cost A. Create Guest List -- 8 4 \ 200 \ 310 B. Send Invitations A 2 1 \ 125 \ 150 C. Plan Decorations A 8 6 \ 300 \ 370 D. Plan Menu A 3 2 \ 150 \ 210 E. Shop D 4 2 \ 475 \ 550 F. Prepare Food E 5 3 \ 225 \ 475
-Based on critical chain concepts, which of the following is true of a resource buffer?
(Multiple Choice)
4.9/5
(33)
The next three questions are related to the project schedule shown below, which has been adjusted to accommodate resource constraints.
-Given the way the schedule shown above is currently planned, what sequence of activities comprises the critical chain? Dashed lines = float.)

(Multiple Choice)
4.7/5
(40)
In critical chain terminology, removing some of the time buffer from individual activity estimates and moving them collectively to the end of the project is an example of:
(Multiple Choice)
4.8/5
(27)
Which of the following would NOT be considered a direct activity cost?
(Multiple Choice)
4.8/5
(34)
The next three questions are related to the project schedule shown below, which has been adjusted to accommodate resource constraints.
-In the network shown above, where would a resource buffer be most appropriate from among the options below?

(Multiple Choice)
4.9/5
(35)
What is the difference between the critical path and the critical chain?
(Multiple Choice)
4.9/5
(36)