Exam 13: Developing and Implementing Effective Accounting Information Systems
Exam 1: Accounting Information Systems and the Accountant87 Questions
Exam 2: Accounting on the Internet124 Questions
Exam 3: Information Technology and Aiss128 Questions
Exam 4: Accounting and Data Analytics43 Questions
Exam 5: Integrated Accounting and Enterprise Software102 Questions
Exam 6: Introduction to Internal Control Systems and Risk Management73 Questions
Exam 7: Computer Controls for Organizations and Accounting Information Systems96 Questions
Exam 8: Accounting Information Systems and Business Processes: Part I51 Questions
Exam 9: Accounting Information Systems and Business Processes: Part II50 Questions
Exam 10: Cybercrime, Fraud, and Ethics75 Questions
Exam 11: Information Technology Auditing67 Questions
Exam 12: Documenting Accounting Information Systems68 Questions
Exam 13: Developing and Implementing Effective Accounting Information Systems128 Questions
Exam 14: Database Design112 Questions
Exam 15: Organizing and Manipulating the Data in Databases79 Questions
Exam 16: Database Forms and Reports61 Questions
Select questions type
"Schedule feasibility" is not important to a study team if a company already has an automated system.
Free
(True/False)
5.0/5
(38)
Correct Answer:
False
The term "cost/benefit" is most closely associated with the economic feasibility of a proposed accounting information system.
Free
(True/False)
4.8/5
(32)
Correct Answer:
True
The term "RFP" stands for "reference project."
Free
(True/False)
4.8/5
(28)
Correct Answer:
False
Which of these is not a phase in the life cycle of an information system?
(Multiple Choice)
4.7/5
(39)
When developing the specifications for a new AIS, designers begin with outputs-not inputs or processing requirements.
(True/False)
4.8/5
(26)
In a PERT network diagram, the amount of delay time that can occur in a non-critical activity and still not delay the estimated completion time of a systems implementation project is called:
(Multiple Choice)
4.9/5
(43)
The tasks involved in "systems maintenance" are normally performed by external vendors, and rarely by a company's internal information systems department.
(True/False)
4.9/5
(37)
Employee behavioral problems are rarely important in systems analysis and design work because most systems are computer-based, not human-based.
(True/False)
4.8/5
(24)
Which of these is not a logical procedure that is followed in the systems analysis phase of a systems study?
(Multiple Choice)
4.8/5
(35)
A "turnkey" computer system is a complete set of computer hardware and software that allows the user to avoid technical decisions and to begin operating quickly.
(True/False)
4.7/5
(34)
In designing an AIS, system developers should design the outputs of the system first, not the inputs.
(True/False)
4.7/5
(30)
In conducting a feasibility study, operational feasibility refers to whether:
(Multiple Choice)
4.8/5
(41)
After successfully implementing a new system, what activities should the implementation team normally perform in their follow-up work?
(Multiple Choice)
4.8/5
(36)
The "slack time" for a PERT activity represents the amount of time the activity can be delayed without delaying the entire project.
(True/False)
4.9/5
(36)
Which of the following is not a general objective when designing an AIS?
(Multiple Choice)
4.9/5
(34)
An advantage of prototyping is that models are usually developed without the aid of a computer.
(True/False)
4.8/5
(47)
Showing 1 - 20 of 128
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)