Exam 8: Flexible Budget and Variance Analysis

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

The Vito Company makes tables for which the following standards have been developed: Standard Inputs Standard Price Expected for Each Expected per Unit of Output Unit of Output Direct materials 10 pounds \ 4 per pound Direct labor 4 hours \ 20 per hour Production of 200 tables was expected in August, but 220 tables were actually completed. Direct materials purchased and used were 2,100 pounds at an actual price of $4.40 per pound. Direct labor cost for the month was $10,620, and the actual pay per hour was $18.00. _ is the standard labor cost for each table produced.

(Multiple Choice)
4.9/5
(24)

The following information is for Pepper Pike Corporation: Direct Material Standard price per unit of input \ 25 Actual price p er unit of input \ 24 Standard inputs allowed p er unit of output 3 pounds Actual units of input 8,300 pounds Actual units of output 2,770 units * Direct material is measured in pounds is the direct- material usage variance.

(Multiple Choice)
4.8/5
(33)

Using standard costs is popular with companies in the United States.

(True/False)
4.9/5
(31)

Job set- up costs for Rob Ublind Company are variable costs based on the number of jobs. Rob Ublind Company expected to work 600 jobs at a total cost of $189,000. Rob Ublind Company worked a total of 630 jobs and actual job set- up costs totaled $177,000. Required: Compute the master budget variance, activity- level variance, and flexible- budget variance for job set- up costs.

(Essay)
4.7/5
(42)

Materials price variance = (actual price - standard price) x standard quantity allowed.

(True/False)
4.7/5
(39)

The Green Company makes chairs for which the following standards have been developed: Standard Inputs Standard Price Expected for E ach Expected per Unit of Output Unit of Output Direct materials 10 pounds \ 4 per pound Direct labor 2 hours \ 23 per hour Production of 250 chairs was expected in March, but 300 chairs were actually completed. Direct materials purchased and used were 2,700 pounds at an actual price of $4.40 per pound. Direct labor cost for the month was $10,620, and the actual pay per hour was $19.00. _ is the standard direct- material cost for each chair produced.

(Multiple Choice)
4.7/5
(31)

(Actual price - standard price) x actual quantity

(Short Answer)
4.9/5
(38)

If the total sales- activity variance was $7,500 favorable, and the total master budget variance was $10,000 favorable, then the total flexible budget variance must have been:

(Multiple Choice)
5.0/5
(39)

is most likely to be held directly accountable for a usage variance.

(Multiple Choice)
4.9/5
(33)

Actual expenses are greater than budgeted expenses

(Short Answer)
4.7/5
(41)

Which of the following is not a true statement?

(Multiple Choice)
4.9/5
(43)

Identify which statement below would not be a possible reason for a variance between a flexible budget and actual results.

(Multiple Choice)
4.8/5
(32)

Beachwood Company produces 2,500 units. Each unit was expected to require 2 labor hours at a cost of $10 per hour. Total labor cost was $55,250 for 4,750 hours worked. Direct labor is measured in hours. _ is the direct- labor price variance.

(Multiple Choice)
4.8/5
(39)

An activity- based budget is based on budgeted costs for every activity and related cost driver.

(True/False)
4.9/5
(36)

Most organizations believe that it is not worthwhile to monitor individual overhead to the same extent as labor and material variances.

(True/False)
4.9/5
(28)

Efficiency is the degree to which a goal, objective, or target is met.

(True/False)
4.7/5
(38)

By using a flexible budget, changes in activity level cannot cause any variances between the flexible budget and actual results.

(True/False)
4.9/5
(36)

Identify which of the statements below is not a reason why actual results would differ from those projected in the master budget.

(Multiple Choice)
4.9/5
(31)

Rockford Company planned to produce 12,000 units. Processing required 16,000 machine hours at a cost of $15,000 + $10.50 per machine hour. Actual sales were 14,000 units requiring 20,000 machine hours. Actual processing cost was $222,000. is the master budget amount for processing.

(Multiple Choice)
4.8/5
(38)

The Beach Company currently produces sandals in an automated process. Expected production per month is 20,000 units. The required direct materials cost is $1.50 per unit. Manufacturing fixed overhead costs are $30,000 per month. Manufacturing overhead is allocated based on units of production. is the flexible budget for 15,000 and 20,000 units, respectively.

(Multiple Choice)
4.8/5
(39)
Showing 21 - 40 of 166
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)