Exam 19: Scheduling
Exam 1: Operations and Supply Chain Management65 Questions
Exam 2: Strategy and Sustainability63 Questions
Exam 3: Product and Service Design55 Questions
Exam 4: Strategic Capacity Management66 Questions
Exam 5: Process Analysis54 Questions
Exam 6: Production Processes46 Questions
Exam 7: Service Processes66 Questions
Exam 8: Health Care Processes60 Questions
Exam 9: Six-Sigma Quality66 Questions
Exam 10: Projects70 Questions
Exam 11: Global Sourcing and Procurement64 Questions
Exam 12: Location, Logistics and Distribution53 Questions
Exam 13: Lean and Sustainable Supply Chains70 Questions
Exam 14: Enterprise Resource Planning Systems37 Questions
Exam 15: Demand Management and Forecasting75 Questions
Exam 16: Sales and Operations Planning60 Questions
Exam 17: Inventory Control71 Questions
Exam 18: Material Requirements Planning66 Questions
Exam 19: Scheduling57 Questions
Exam 20: Constraint Management56 Questions
Select questions type
Assume there are five jobs (i.e., A, B, C, D and E) that need to be sequenced in a production schedule.The remaining operating time necessary for completion of job A is 3 days (i.e., job A will take 3 more days to complete), B will take 9 days, C will take 6 days, D will take 5 days and E will take 8 days.In what order will these jobs be scheduled if using the SOT priority rule for job sequencing?
Free
(Multiple Choice)
4.9/5
(49)
Correct Answer:
B
A job has 10 days of processing time left to do before completion and today is the 5th day of the month.If the job is due on the 15th day of the month, what is its critical ratio?
Free
(Multiple Choice)
4.8/5
(33)
Correct Answer:
C
Which of the following is a priority rule used to schedule the sequence of jobs in a production operation?
Free
(Multiple Choice)
4.7/5
(27)
Correct Answer:
A
Which of the following is not a function performed in scheduling and controlling an operation?
(Multiple Choice)
4.7/5
(27)
Which of the following priority rules used in scheduling the sequence of production is calculated as the time remaining before the due date minus the remaining processing time, with the smallest value being run first?
(Multiple Choice)
4.7/5
(40)
A job has 5 days of processing time left to do before completion and today is the 10th day of the month.If the job is due on the 14th day of the month, what is its critical ratio?
(Multiple Choice)
4.8/5
(36)
One of the principles of work center scheduling is that, while certainty of standards, routings, and so forth is not entirely possible in a shop, certainty should always be an objective to work towards.
(True/False)
4.7/5
(39)
Initiating performance of scheduled work is commonly termed "dispatching" of orders.
(True/False)
4.8/5
(26)
Under the STR/OP sequencing priority rule, orders with the jobs with the longest STR/OP are run first.
(True/False)
4.9/5
(34)
A backward schedule tells when an order must be started in order to be done by a specific date.
(True/False)
4.8/5
(40)
A system that "backward schedules" is designed to determine and report the earliest date an order can be completed.
(True/False)
4.8/5
(36)
One of the principles of work center scheduling is that the effectiveness of any shop should be measured by speed of flow through the shop.
(True/False)
4.8/5
(41)
One of the principles of work center scheduling is to match work center input information to what the worker can actually do.
(True/False)
4.8/5
(38)
Which of the following might be a status and exception report used in shop-floor control?
(Multiple Choice)
4.9/5
(27)
Which of the following priority rules used in scheduling the sequence of production is calculated as the slack time remaining in the schedule divided by the number of remaining operations, with the smallest value being run first?
(Multiple Choice)
4.9/5
(33)
A material requirements planning system is an example of which of the following scheduling systems?
(Multiple Choice)
4.7/5
(40)
For a continuous process type of manufacturing which of the following is the typical production scheduling approach?
(Multiple Choice)
4.9/5
(40)
Assume there are five jobs (i.e., A, B, C, D and E) that need to be sequenced in a production schedule.The remaining operating time necessary for completion of job A is 4 days (i.e., job A will take 4 more days to complete), B will take 7 days, C will take 8 days, D will take 2 days, and E will take 5 days, which job should be scheduled first if you use the SOT priority rule for job sequencing?
(Multiple Choice)
4.7/5
(42)
Theoretically, all schedules are feasible when finite loading is used.
(True/False)
4.9/5
(36)
Using the random order or "whim" priority rule to sequence production jobs means that supervisors or operators select whichever job they feel like running.
(True/False)
4.9/5
(32)
Showing 1 - 20 of 57
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)