Exam 10: Projects

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Derivative projects are those which address incremental changes to products or processes.

Free
(True/False)
5.0/5
(31)
Correct Answer:
Verified

True

Earned Value Management (EVM) is a technique for measuring project progress in an objective manner.

Free
(True/False)
4.9/5
(36)
Correct Answer:
Verified

True

The valuations in an Earned Value Management analysis must be either profits or revenue.

Free
(True/False)
4.9/5
(28)
Correct Answer:
Verified

False

A matrix project structure is often referred to as a "skunkworks."

(True/False)
4.8/5
(33)

Project management software available today combines CPM and other scheduling aids, like Gantt charting, to aid in tracking progress of project completion.

(True/False)
4.8/5
(39)

For an activity in a CPM analysis, the Early Start time is 8 and the Late Start time is 10.Which of the following statements is ?

(Multiple Choice)
4.8/5
(33)

A company must perform a maintenance project consisting of seven activities.The activities, their predecessors, and their respective time estimates are presented below: A company must perform a maintenance project consisting of seven activities.The activities, their predecessors, and their respective time estimates are presented below:   Using CPM, which activities have slack in this project? Using CPM, which activities have slack in this project?

(Multiple Choice)
4.9/5
(32)

Below are the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the costs include both direct and indirect costs. Below are the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the costs include both direct and indirect costs.   What are the total time of this project and total normal cost? What are the total time of this project and total normal cost?

(Multiple Choice)
4.9/5
(39)

Calculating the early start and early finish times for each activity in a CPM analysis does not provide any useful information.

(True/False)
4.8/5
(39)

A listing of immediate predecessor activities is important information in a CPM analysis for which of the following reasons?

(Multiple Choice)
4.8/5
(36)

You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below. You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project direct costs are given below.   The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400, 15 days they will be $250, 14 days they will be $200, and 13 days they will be $100.If you crash this project by one day what is the total (i.e., direct and indirect) project cost? The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400, 15 days they will be $250, 14 days they will be $200, and 13 days they will be $100.If you crash this project by one day what is the total (i.e., direct and indirect) project cost?

(Multiple Choice)
4.9/5
(39)

Slack activity time is the difference between the early start and the late finish of a project activity time.

(True/False)
4.9/5
(36)

Upper level management must decide between pure, functional, and matrix structures as ways to organize projects.

(True/False)
4.7/5
(39)

PERT is an abbreviation for which of the following methodologies?

(Multiple Choice)
4.8/5
(35)

A series of projects that are organized in such a way that each project utilizes people from different functional areas is using which of the following organizational structures?

(Multiple Choice)
4.8/5
(36)

You are looking at a chart that has the terms BCWS, BCWP and AC indicating lines on the chart.What kind of chart are you looking at?

(Multiple Choice)
4.8/5
(29)

A project milestone is a specific event to be reached by a particular point in time.

(True/False)
4.8/5
(34)

Some of the advantages of a functional project where the project is housed in a functional division include which of the following?

(Multiple Choice)
4.8/5
(35)

The Gantt chart is an example of a project control chart.

(True/False)
4.8/5
(36)

In a CPM analysis if you subtract the early start from the late start the result is the activity's slack time.

(True/False)
4.8/5
(36)