Exam 20: Constraint Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A way to find a bottleneck is to use one's knowledge of a particular plant, look at the system in operation, and talk with supervisors and workers.

Free
(True/False)
4.8/5
(35)
Correct Answer:
Verified

True

According to the theory of constraints, throughput is the rate at which product is passed through the manufacturing system.

Free
(True/False)
4.9/5
(41)
Correct Answer:
Verified

False

The effects of statistical variations in processing times in a dependent sequence will eventually cancel themselves out due to the law of averages.

Free
(True/False)
4.8/5
(35)
Correct Answer:
Verified

False

A useful measure of inventory performance is called "dollar days." In which of the following areas are dollar days measurements not useful?

(Multiple Choice)
4.9/5
(42)

In a process sequence where a product flows from process A to process B, process A is called the "mother" process.

(True/False)
4.7/5
(29)

A synchronous manufacturing system does not have excess capacity throughout the system, except for the bottleneck.

(True/False)
4.8/5
(32)

According to the theory of constraints which of the following is a financial measurement that can be used to measure the firm's ability to make money?

(Multiple Choice)
4.8/5
(40)

A process batch should be no larger than the transfer batch.

(True/False)
4.9/5
(47)

The operational measure of throughput is "the rate at which money is generated by the system through production of goods and services that might be sold."

(True/False)
4.8/5
(31)

The "dollar days" inventory measurement results from a complex algorithm used to compute individual units of inventory and their respective ordering and holding costs.

(True/False)
4.8/5
(37)

One way to find a bottleneck is to run a capacity resource profile.

(True/False)
4.8/5
(37)

OPT stands for optimal purchasing technique.

(True/False)
4.8/5
(37)

Which of the following is a negative aspect of JIT compared to synchronous manufacturing?

(Multiple Choice)
4.8/5
(42)

Mr.Goldratt's "Theory of Constraints" is useful only in manufacturing settings.

(True/False)
5.0/5
(38)

JIT requires work-in-process when used with kanban so there is inventory to pull.When compared to synchronous manufacturing this is viewed as a negative aspect of JIT.

(True/False)
4.7/5
(40)

On an assembly line a transfer batch can be one unit.

(True/False)
4.9/5
(36)

Looking at the loads that are placed on each resource by the products that are scheduled through them is called process flow profiling.

(True/False)
4.8/5
(35)

Departments within a firm often are at odds with each other because reward systems are often not synchronized with the basic goal of the firm: to make money.

(True/False)
4.8/5
(37)

Which of the following is one of Dr.Eli Goldratt's rules of production scheduling for optimized production technology?

(Multiple Choice)
4.8/5
(36)

From an operations standpoint, one of the goals of the firm under the theory of constraints is to increase throughput while simultaneously reducing inventory and reducing operating expense.

(True/False)
4.8/5
(29)
Showing 1 - 20 of 56