Define the critical path and explain its importance

Free
(Essay)
4.9/5
(32)
Correct Answer:
Verified

The critical path is determined by constructing a network representation of a project that captures all of the precedence relationships among activities. The critical path is the set of activities that must be completed exactly on time in order to keep the project on schedule. By definition, there is no slack for completing the activities on the critical path, as delaying any one of them will delay in the completion time of the entire project.

Explain how and when a project's risk is addressed in the project management lifecycle.

Free
(Essay)
4.8/5
(32)
Correct Answer:
Verified

The risks associated with the project are assessed at the planning stage. A risk plan will be developed, identifying the major risks, their potential impact, and methods for avoiding or minimizing them.

What is a project charter?

Free
(Essay)
4.7/5
(26)
Correct Answer:
Verified

It is a document defining the terms of reference of a project, that is, what the project is intended to achieve, and the approximate timeline and resources available.

A new bridge project passed the feasibility study test, and is now in the planning stage. The project manager thinks that evaluation of people's willingness to pay for the use of the bridge was done under the assumption of low inflation. In this regard, at this stage the project manager should

(Multiple Choice)
4.9/5
(33)

Nodes and arcs are used in the following project management tool:

(Multiple Choice)
4.8/5
(33)

"CPM" stands for

(Multiple Choice)
4.7/5
(33)

What is a Gantt Chart?

(Essay)
4.9/5
(38)

Describe three "best practices" to observe when producing a WBS?

(Essay)
4.8/5
(37)

What are the advantages and disadvantages of a Gantt Chart?

(Essay)
4.8/5
(34)

For an engineering project, the justification for the project is defined in the

(Multiple Choice)
4.9/5
(41)

A fundamental advantage of the CPM networks project management tool is that it provides

(Multiple Choice)
4.8/5
(34)

How do we find a project's critical path?

(Essay)
4.9/5
(31)

The AON diagram shown represents a project. Normal and crash times, and the associated costs, are shown for each activity in the accompanying table. The normal completion time for the project is 130 weeks. If it is worth $10 000 a week to reduce the project duration, what is the shortest economical crash time? The AON diagram shown represents a project. Normal and crash times, and the associated costs, are shown for each activity in the accompanying table. The normal completion time for the project is 130 weeks. If it is worth $10 000 a week to reduce the project duration, what is the shortest economical crash time?    The AON diagram shown represents a project. Normal and crash times, and the associated costs, are shown for each activity in the accompanying table. The normal completion time for the project is 130 weeks. If it is worth $10 000 a week to reduce the project duration, what is the shortest economical crash time?

(Multiple Choice)
4.9/5
(24)

Project execution includes

(Multiple Choice)
4.9/5
(37)

What is meant by "crashing a project"?

(Essay)
4.7/5
(32)

In a single sentence, what is project management?

(Essay)
4.9/5
(43)

In crashing a project, what should be the first activities you chose to crash?

(Multiple Choice)
4.9/5
(37)

Suppose that the crash cost is $10 million, normal cost is $8 million, normal project time is 10 years and crash time is 8 years, what is the project's crash cost per year?

(Multiple Choice)
4.8/5
(35)

A Gantt Chart is

(Multiple Choice)
4.9/5
(26)

When resources such as overtime, extra equipment, and additional staff result in higher costs, what should a project manager do?

(Multiple Choice)
4.9/5
(30)