Exam 15: Lean and Six Sigma Management and Leading Change

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

The kanban card that has a requisition for parts or components is called the ________ card.

Free
(Short Answer)
4.9/5
(29)
Correct Answer:
Verified

supplier

Specially trained individuals in advanced quality tools who perform Six Sigma projects are known as ________.

Free
(Short Answer)
4.8/5
(33)
Correct Answer:
Verified

black belts

The Japanese term for continuous improvement is kaizen.

Free
(True/False)
4.7/5
(35)
Correct Answer:
Verified

True

A lean method that gives employees the authority to stop the production line when a problem has occurred that triggers a machine stop is known as ________.

(Short Answer)
4.9/5
(38)

What is value analysis and value engineering? What is its role in the lean philosophy?

(Essay)
4.9/5
(35)

Which type of kanban card usually contains bill of materials information for incoming parts or components?

(Multiple Choice)
4.8/5
(41)

The letter "D" in the Six Sigma acronym DMAIC stands for

(Multiple Choice)
4.8/5
(36)

Specially trained individuals in advanced quality tools who perform Six Sigma projects are known as green belts.

(True/False)
4.8/5
(32)

The first business to implement Six Sigma was Toyota.

(True/False)
4.9/5
(30)

The Japanese term for continuous improvement is ________.

(Short Answer)
4.8/5
(38)

What does the word "Six" in Six Sigma refer to?

(Essay)
4.8/5
(39)

Which type of kanban card is used to transport parts from one location to another?

(Multiple Choice)
4.7/5
(29)

Fast improvement focussing on a finite problem is known as ________.

(Short Answer)
4.9/5
(29)

In a production plant,800 parts per day are needed.A standard container holds 100 parts.It takes half a day to receive parts once the move card is released.A safety stock of 100 parts is usually maintained.What is the number of kanban cards needed?

(Multiple Choice)
4.8/5
(35)

As per the Risk and Return evaluation matrix for Six Sigma projects,projects that are low hanging fruit have a

(Multiple Choice)
4.9/5
(37)

The task of implementing process changes will be performed in which phase of the Six Sigma DMAIC process?

(Multiple Choice)
5.0/5
(27)

A person trained in basic quality tools related to Six Sigma projects is known as a ________.

(Short Answer)
4.8/5
(29)

The practice of "producing a little bit of everything,everyday" attained by making setup times short is known as ________.

(Short Answer)
4.8/5
(34)

What are the seven wastes identified by Shigeo Shingo's in a process?

(Essay)
4.8/5
(36)

The task of selecting process outcomes will be performed in which phase of the Six Sigma DMAIC process?

(Multiple Choice)
4.9/5
(28)