Documentation that tells buyers what to buy and the suppliers what is required of them is known as ________.

Free
(Short Answer)
4.7/5
(39)
Correct Answer:
Verified

specification

Use the information below to answer the following question(s). A computer manufacturer procures memory chips from its key supplier. The tool that the manufacturer uses to monitor the part supplier is a supplier scorecard. With respect to delivery performance,the primary performance metric monitored is the percentage of orders delivered complete and on-time. The manufacturer also monitors the supplier's service performance and measures the invoice accuracy rate (% of invoices that are accurate). The following measures are used for the scoring criteria: Percentage of orders delivered complete \ Scorecard and on-time Points 95-100 25 90-95 20 80-90 10 >80 0  Use the information below to answer the following question(s). A computer manufacturer procures memory chips from its key supplier. The tool that the manufacturer uses to monitor the part supplier is a supplier scorecard. With respect to delivery performance,the primary performance metric monitored is the percentage of orders delivered complete and on-time. The manufacturer also monitors the supplier's service performance and measures the invoice accuracy rate (% of invoices that are accurate). The following measures are used for the scoring criteria:   \begin{array} { | l | l | }  \hline \begin{array} { l }  \text { Percentage of orders } \\ \text { delivered complete } \end{array} & \ { \text { Scorecard } } \\  \text { and on-time } & \text { Points } \\ \hline 95 - 100 & 25 \\ \hline 90 - 95 & 20 \\ \hline 80 - 90 & 10 \\ \hline > 80 & 0 \\ \hline \end{array}       Data collected on the supplied orders over the present quarter indicated that 350 orders were delivered and out of these 10 orders were incomplete,5 orders were late and another 15 orders were incomplete and late. Also out the 350 invoices for the shipments delivered,there were errors on 50 invoices. -What is the delivery performance-i.e.,percentage of order delivered complete and on-time for this quarter? Data collected on the supplied orders over the present quarter indicated that 350 orders were delivered and out of these 10 orders were incomplete,5 orders were late and another 15 orders were incomplete and late. Also out the 350 invoices for the shipments delivered,there were errors on 50 invoices. -What is the delivery performance-i.e.,percentage of order delivered complete and on-time for this quarter?

Free
(Multiple Choice)
4.8/5
(33)
Correct Answer:
Verified

B

A transactional relationship with the supplier is usually recommended for the procurement of a critical item.

Free
(True/False)
4.8/5
(30)
Correct Answer:
Verified

False

Use the information below to answer the following question(s). A computer manufacturer procures memory chips from its key supplier. The tool that the manufacturer uses to monitor the part supplier is a supplier scorecard. With respect to delivery performance,the primary performance metric monitored is the percentage of orders delivered complete and on-time. The manufacturer also monitors the supplier's service performance and measures the invoice accuracy rate (% of invoices that are accurate). The following measures are used for the scoring criteria: Percentage of orders delivered complete \ Scorecard and on-time Points 95-100 25 90-95 20 80-90 10 >80 0  Use the information below to answer the following question(s). A computer manufacturer procures memory chips from its key supplier. The tool that the manufacturer uses to monitor the part supplier is a supplier scorecard. With respect to delivery performance,the primary performance metric monitored is the percentage of orders delivered complete and on-time. The manufacturer also monitors the supplier's service performance and measures the invoice accuracy rate (% of invoices that are accurate). The following measures are used for the scoring criteria:   \begin{array} { | l | l | }  \hline \begin{array} { l }  \text { Percentage of orders } \\ \text { delivered complete } \end{array} & \ { \text { Scorecard } } \\  \text { and on-time } & \text { Points } \\ \hline 95 - 100 & 25 \\ \hline 90 - 95 & 20 \\ \hline 80 - 90 & 10 \\ \hline > 80 & 0 \\ \hline \end{array}       Data collected on the supplied orders over the present quarter indicated that 350 orders were delivered and out of these 10 orders were incomplete,5 orders were late and another 15 orders were incomplete and late. Also out the 350 invoices for the shipments delivered,there were errors on 50 invoices. -What are the scorecard points received by this supplier for the service performance in this quarter? Data collected on the supplied orders over the present quarter indicated that 350 orders were delivered and out of these 10 orders were incomplete,5 orders were late and another 15 orders were incomplete and late. Also out the 350 invoices for the shipments delivered,there were errors on 50 invoices. -What are the scorecard points received by this supplier for the service performance in this quarter?

(Multiple Choice)
4.9/5
(45)

The table below contains a list of four companies that have been rated (on a 1 to 5 scale)on three weighted performance factors.What is the score for Phoenix? Performance Factors Weight Excelsior Phoenix Mega American Quality 0.50 4 4 2 4 Cost 0.40 4 3 5 3 Speed 0.10 2 2 4 5

(Multiple Choice)
4.9/5
(32)

Discuss the role/ purpose of a request for quote (RFQ)or a request for proposal (RFP)in the procurement process.

(Essay)
4.8/5
(35)

Use the information below to answer the following question(s). A computer manufacturer procures memory chips from its key supplier. The tool that the manufacturer uses to monitor the part supplier is a supplier scorecard. With respect to delivery performance,the primary performance metric monitored is the percentage of orders delivered complete and on-time. The manufacturer also monitors the supplier's service performance and measures the invoice accuracy rate (% of invoices that are accurate). The following measures are used for the scoring criteria: Percentage of orders delivered complete \ Scorecard and on-time Points 95-100 25 90-95 20 80-90 10 >80 0  Use the information below to answer the following question(s). A computer manufacturer procures memory chips from its key supplier. The tool that the manufacturer uses to monitor the part supplier is a supplier scorecard. With respect to delivery performance,the primary performance metric monitored is the percentage of orders delivered complete and on-time. The manufacturer also monitors the supplier's service performance and measures the invoice accuracy rate (% of invoices that are accurate). The following measures are used for the scoring criteria:   \begin{array} { | l | l | }  \hline \begin{array} { l }  \text { Percentage of orders } \\ \text { delivered complete } \end{array} & \ { \text { Scorecard } } \\  \text { and on-time } & \text { Points } \\ \hline 95 - 100 & 25 \\ \hline 90 - 95 & 20 \\ \hline 80 - 90 & 10 \\ \hline > 80 & 0 \\ \hline \end{array}       Data collected on the supplied orders over the present quarter indicated that 350 orders were delivered and out of these 10 orders were incomplete,5 orders were late and another 15 orders were incomplete and late. Also out the 350 invoices for the shipments delivered,there were errors on 50 invoices. -What is the service performance-i.e.,percentage of invoices that are accurate for this quarter? Data collected on the supplied orders over the present quarter indicated that 350 orders were delivered and out of these 10 orders were incomplete,5 orders were late and another 15 orders were incomplete and late. Also out the 350 invoices for the shipments delivered,there were errors on 50 invoices. -What is the service performance-i.e.,percentage of invoices that are accurate for this quarter?

(Multiple Choice)
4.8/5
(32)

A supplier scorecard is used for price negotiations with the supplier.

(True/False)
4.8/5
(32)

The first step in the supplier development process is to identify opportunities for development.

(True/False)
4.8/5
(34)

Which is the last step in the supplier management process?

(Multiple Choice)
4.9/5
(40)

The document which contains the specifications of what is needed and details the information that must be submitted by a supplier is known as ________.

(Essay)
4.9/5
(31)

The first step in the process of designing and implementing a supplier scorecard is to develop the performance measures.

(True/False)
4.7/5
(27)

The supplier development process is the sole responsibility of mid-level management.

(True/False)
4.9/5
(34)

Use the information below to answer the following question(s). An automotive manufacturer procures an important engine part. The tool that the manufacturer uses to monitor the part supplier is a supplier scorecard. With respect to part quality,two primary performance metrics monitored are parts per million (PPM)defects and percent PPM improvement. The following measures are used for the scoring criteria: PPM Defect Scorecard \ Rate Points 0-100 30 100-200 20 200-300 10 >300 0 Percent PPM Scorecard improvement Points 75-100 15 50-74 10 25-49 5 <25 0 Data collected on the supplied part over the present quarter indicated 15 defects with 325,000 parts received. The PPM defect rate in the prior quarter was 73. -What is the PPM defect rate for this quarter?

(Multiple Choice)
4.7/5
(37)

Use the information below to answer the following question(s). An automotive manufacturer procures an important engine part. The tool that the manufacturer uses to monitor the part supplier is a supplier scorecard. With respect to part quality,two primary performance metrics monitored are parts per million (PPM)defects and percent PPM improvement. The following measures are used for the scoring criteria: PPM Defect Scorecard \ Rate Points 0-100 30 100-200 20 200-300 10 >300 0 Percent PPM Scorecard improvement Points 75-100 15 50-74 10 25-49 5 <25 0 Data collected on the supplied part over the present quarter indicated 15 defects with 325,000 parts received. The PPM defect rate in the prior quarter was 73. -What are the scorecard points received by this supplier for the PPM defect rate in this quarter?

(Multiple Choice)
4.8/5
(42)

The first step in the process of designing and implementing a supplier scorecard is to ________.

(Short Answer)
4.8/5
(32)

The final step in the process of designing and implementing a supplier scorecard is to ________.

(Short Answer)
4.8/5
(30)

Which of the following suppliers is not a prime candidate to be chosen as part of the supplier development process?

(Multiple Choice)
4.7/5
(31)

Use the information below to answer the following question(s). An automotive manufacturer procures an important engine part. The tool that the manufacturer uses to monitor the part supplier is a supplier scorecard. With respect to part quality,two primary performance metrics monitored are parts per million (PPM)defects and percent PPM improvement. The following measures are used for the scoring criteria: PPM Defect Scorecard \ Rate Points 0-100 30 100-200 20 200-300 10 >300 0 Percent PPM Scorecard improvement Points 75-100 15 50-74 10 25-49 5 <25 0 Data collected on the supplied part over the present quarter indicated 15 defects with 325,000 parts received. The PPM defect rate in the prior quarter was 73. -What is the percent improvement in the defect rate this quarter compared to the prior quarter?

(Multiple Choice)
4.7/5
(27)

Self-assessment to provide accurate and timely feedback during the negotiating team should occur during which step of the negotiation process?