Exam 23: Theory of Constraints

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Which of the following is an approach to dealing with a bottleneck?

Free
(Multiple Choice)
5.0/5
(30)
Correct Answer:
Verified

A

A way to find a bottleneck is to use one's knowledge of a particular plant, look at the system in operation, and talk with supervisors and workers.

Free
(True/False)
4.9/5
(30)
Correct Answer:
Verified

True

Buffer inventory in front of a bottleneck is called a time buffer.

Free
(True/False)
4.8/5
(41)
Correct Answer:
Verified

True

Departments within a firm often are at odds with each other because reward systems are often not synchronized with the basic goal of the firm: to make money.

(True/False)
4.8/5
(40)

The "dollar days" inventory measurement can be used in purchasing to discourage large work-in-process and producing earlier than is needed.

(True/False)
4.8/5
(27)

Which of the following is a "focusing step" of Dr.Eli Goldratt's theory of constraints?

(Multiple Choice)
4.9/5
(41)

According to the theory of constraints, which of the following is a kind of time that makes up the cycle time in production?

(Multiple Choice)
4.9/5
(21)

According to the theory of constraints, which of the following is a financial measurement that can be used to measure the firm's ability to make money?

(Multiple Choice)
4.9/5
(27)

The "dollar days" inventory measurement may be used to focus management's attention on where inventory is located.

(True/False)
4.8/5
(30)

A useful measure of inventory performance is called "dollar days." In which of the following areas are dollar days measurements not useful?

(Multiple Choice)
4.8/5
(29)

According to the theory of constraints, a capacity-constrained resource (CCR) is one whose utilization is close to capacity and could be a bottleneck if it is not scheduled carefully.

(True/False)
4.8/5
(34)

Looking at the loads that are placed on each resource by the products that are scheduled through them is called process flow profiling.

(True/False)
4.8/5
(23)

The term "dependent events" refers to a process sequence.

(True/False)
4.8/5
(39)

According to the theory of constraints, which of the following is an operational measurement that can be used to measure the firm's ability to make money?

(Multiple Choice)
4.7/5
(35)

From an operations standpoint, one of the goals of the firm under the theory of constraints is to increase throughput while simultaneously reducing inventory and reducing operating expense.

(True/False)
4.8/5
(35)

On an assembly line, a transfer batch can be one unit.

(True/False)
4.7/5
(37)

According to the theory of constraints, throughput is the rate at which product is passed through the manufacturing system.

(True/False)
4.9/5
(27)

Synchronous manufacturing refers to the entire production process working together in harmony to achieve the goals of the firm.

(True/False)
5.0/5
(39)

According to the theory of constraints, the term "productivity" is defined as all those actions that bring a company closer to its goals.

(True/False)
4.8/5
(33)

Which of the following is a negative aspect of JIT compared to synchronous manufacturing?

(Multiple Choice)
4.8/5
(42)
Showing 1 - 20 of 55