Resources cannot be added to the tasks shown in the Gantt chart.

(True/False)
4.8/5
(32)

MS Project is a full-service project management software because it focuses on

(Multiple Choice)
4.8/5
(33)

The resource sheet allows you to enter people that will be working on a project to the project.

(True/False)
5.0/5
(37)

Project provides a variety of screens to capture the full picture of the project.

(True/False)
4.9/5
(36)

MS Project allows a project manager to control resources.

(True/False)
4.9/5
(30)

The data entry in the resource sheet is the same as for the

(Multiple Choice)
4.8/5
(35)

In the resource view you see ________ available to the project

(Multiple Choice)
5.0/5
(31)

When you create subtasks the tasks associated with those subtasks automatically get the

(Multiple Choice)
4.8/5
(37)

The ________ is located on the far left hand side of the screen.

(Multiple Choice)
4.9/5
(44)

A Tracking Gantt allows a project manager to track the progress of a project against a baseline.

(True/False)
4.8/5
(30)

MS Project is a full-service project management process software.

(True/False)
4.8/5
(31)

The resource usage view would allow a project manager to better control resources like overtime.

(True/False)
4.9/5
(38)