Exam 2: System Development, Requirements Analysis, and Risk Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Choose the correct option according to the given statements regarding risk management.Statement 1: A risk is a potential problem-it might happen, it might not. Statement 2: Managers, software engineers, and customers participate in risk analysis and management. Statement 3: Only Managers participate in risk analysis and management.

Free
(Multiple Choice)
4.9/5
(30)
Correct Answer:
Verified

A

What is/are the different types of risk may occur when you develop software?

Free
(Multiple Choice)
4.8/5
(38)
Correct Answer:
Verified

D

Which of the following risks are derived from the organizational environment where the software is being developed?

Free
(Multiple Choice)
4.8/5
(21)
Correct Answer:
Verified

D

What are the types of requirement in Quality Function Deployment(QFD) ?

(Multiple Choice)
5.0/5
(39)

Which of the following term is best de?ned by the statement: "Derive traceability information to maximize information hiding in the design."?

(Multiple Choice)
4.8/5
(27)

What is the ?nal outcome of the requirements analysis and speci?cations phase ?

(Multiple Choice)
4.7/5
(38)

Software risk always involves two characteristics. What are those characteristics?

(Multiple Choice)
4.9/5
(33)

Effective risk management plan needs to address which of these issues?

(Multiple Choice)
4.9/5
(41)

Which of the following term is best de?ned by the statement: "There will be a change of organizational management with different priorities."?

(Multiple Choice)
4.9/5
(34)

Which of the following risk is the failure of a purchased component to perform as expected?

(Multiple Choice)
5.0/5
(37)

Traceability is not considered in Requirement Analysis.

(True/False)
4.9/5
(30)

The user system requirements are the parts of which document ?

(Multiple Choice)
4.8/5
(35)

A Use-case actor is always a person having a role that different people may play.

(True/False)
4.8/5
(41)

What assess the risk and your plans for risk mitigation and revise these when you learn more about the risk?

(Multiple Choice)
4.9/5
(38)

Risk management is now recognized as one of the most important project management tasks.

(True/False)
4.8/5
(33)

Which of the following strategies means that the impact of the risk will be reduced?

(Multiple Choice)
4.8/5
(35)

Which of the following term is best de?ned by the statement: "The underlying technology on which the system is built is superseded by new technology."?

(Multiple Choice)
4.7/5
(41)

Risk management is one of the most important jobs for a

(Multiple Choice)
4.8/5
(34)

Reactive risk management is sometimes described as:

(Multiple Choice)
5.0/5
(37)

The phase of System Development associated with creation of the test data is

(Multiple Choice)
4.9/5
(28)