Exam 3: Managing the Information Systems Project

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Projects are deemed a success or failure at project closedown.

(True/False)
4.8/5
(32)

During which of the following project planning activities do you use the information regarding tasks and resource availability to assign time estimates to each activity in the work breakdown structure?

(Multiple Choice)
4.8/5
(36)

Which of the following is True regarding Gantt chart construction?

(Multiple Choice)
4.8/5
(35)

Arguably, the most instrumental person to the successful completion of any project is the:

(Multiple Choice)
4.7/5
(37)

Defining the necessary activities required to organize the initiation team while they are working to define the scope of the project is the focus of which of the following activities?

(Multiple Choice)
4.9/5
(36)

Gantt charts do not show how tasks must be ordered.

(True/False)
4.9/5
(41)

What would be the estimated time for completion if time estimates for installation are as follows? optimistic = 1 week; pessimistic = 1 week; realistic = 1 week

(Multiple Choice)
4.9/5
(38)

The status report project team communication method is used to inform project team members.

(True/False)
4.7/5
(38)

COCOMO uses parameters that are derived from estimates of planned projects of the same complexity to estimate project size and cost.

(True/False)
4.8/5
(34)

Gantt charts visually show the time overlap of tasks whereas a network diagram does not show time overlap but does show which tasks could be done in parallel.

(True/False)
4.8/5
(38)

If an activity's optimistic time is four days, its realistic time is 10 days, and its pessimistic time is 25 days, then its estimated time would be 11.5 days.

(True/False)
4.9/5
(35)

Optimistic time refers to:

(Multiple Choice)
4.8/5
(31)

Ensuring that all contractual terms of the project have been met is done during:

(Multiple Choice)
4.9/5
(36)

A scheduling technique where the order and duration of the sequence of activities directly affect the completion date of a project refers to:

(Multiple Choice)
5.0/5
(26)
Showing 81 - 94 of 94
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)